By Ryan Kramer, founder of Wisegrid. Last updated November 2026.
Smartsheet project management means running a project schedule in a Smartsheet sheet: one row per task, with start date, end date, duration, predecessors and percent complete, shown as a grid or a Gantt chart. When dependencies are turned on, changing one task moves the dates of the tasks that depend on it.
Smartsheet is a capable project tool, and many construction and engineering teams use it well. This guide is for teams setting it up or deciding whether to keep it. It covers the project sheet setup, a worked nine-task schedule that shows how dependencies move dates, what Smartsheet costs as of November 7, 2026, the sheet limits worth planning for, and when a team might look elsewhere.
Key takeaways
– Use a project sheet, not a plain grid. Start date, end date, duration and predecessors are what make the schedule move.
– Dependencies do the real work. One late task pushes every task after it, so the finish date stays honest.
– Check the plan before you build. Smartsheet’s help articles list different plans for dependencies and critical path, so confirm on a trial.
– Plan for the limits. A standard sheet holds 20,000 rows and 500,000 cells; Pro allows 250 automation runs a month.
– Price by editor. Pro costs $9 a member a month billed yearly and Business $19, with free contributors on both.
Is Smartsheet good for project management?
Yes, Smartsheet is a good fit for teams that think in spreadsheets and need schedules with dependencies, shared status and dashboards. It offers grid, Gantt, board and calendar views, predecessors with finish-to-start, start-to-start, finish-to-finish and start-to-finish links, critical path highlighting and baselines that compare planned and actual dates.
It is less suited to very large single schedules, because of its per-sheet limits, and to small teams that only need a task list, because a simpler tool costs less. Our Smartsheet vs Excel comparison and the Smartsheet vs monday.com post cover those trade-offs in more detail.
How do you set up a project sheet in Smartsheet?
You set up a project sheet by adding date columns, turning on dependencies and entering predecessors by row number. These are the columns Smartsheet’s project settings work with.
| Column | Type | What it does |
|---|---|---|
| Task name | Text, primary column | Indent to make phases |
| Start date | Date | Calculated once linked |
| End date | Date | Start plus duration |
| Duration | Duration | Working days, such as 4d |
| Predecessors | Predecessor | Row numbers, such as 3FS |
| % complete | Percent | Drives the Gantt bar fill |
| Assigned to | Contact list | One owner per task |
| Status | Dropdown | Not started to Complete |
Then follow these steps:
- Create the sheet from a blank project template or your own grid, with the columns above.
- Turn on dependencies. In grid and legacy Gantt views this is in Project Settings; in the newer table, board and timeline views it is the Dependencies toggle in sheet settings. Map Duration and Predecessors to your columns.
- Set working days and holidays in the same settings, so durations skip weekends and site shutdowns.
- Indent tasks under phases. Parent rows roll up dates and percent complete from their children.
- Enter predecessors as row numbers, such as 3 or 3FS for finish-to-start, and add lag in working days if one task must wait after another.
- Switch to Gantt view to check the bars, turn on the critical path, and save a baseline once the schedule is approved.
- Share and report. Give the team edit rights, give clients view access, and build a dashboard for status.
One warning from Smartsheet’s own help: typing a date by hand into a row that has a predecessor removes the predecessor link. Change the duration or the predecessor instead.
Worked example: how dependencies move a schedule
Here is a nine-task office renovation scheduled to start on Monday, January 11, 2027, with a five-day work week and no holidays set. The Finish column is the original plan. The last column shows what happens when framing, row 3, takes six days instead of four. Bold rows are on the critical path.
| Task | Days | Pred. | Finish | After slip |
|---|---|---|---|---|
| 1 Mobilize | 2 | Jan 12 | Jan 12 | |
| 2 Demolition | 3 | 1 | Jan 15 | Jan 15 |
| 3 Framing | 4 | 2 | Jan 21 | Jan 25 |
| 4 Rough electrical | 3 | 3 | Jan 26 | Jan 28 |
| 5 Rough plumbing | 2 | 3 | Jan 25 | Jan 27 |
| 6 Inspection | 1 | 4, 5 | Jan 27 | Jan 29 |
| 7 Drywall | 5 | 6 | Feb 3 | Feb 5 |
| 8 Paint | 3 | 7 | Feb 8 | Feb 10 |
| 9 Punch list | 2 | 8 | Feb 10 | Feb 12 |
What this tells you: a two-day slip on framing moved every later task and pushed the finish from Wednesday, February 10 to Friday, February 12, without anyone retyping a date. Rough plumbing is not on the critical path: it finishes a day before rough electrical, so it has one day of float. This is the core reason to use a dependency-based tool instead of a static spreadsheet. Our guide on how to create a construction schedule explains the critical path in more depth.
Watch: Critical Path Explained on a Real Schedule (2 minutes)
Watch “Critical Path Explained on a Real Schedule” on YouTube →
How much does Smartsheet cost for project management?
Smartsheet costs $9 per member a month on Pro and $19 per member a month on Business when billed yearly, or $12 and $24 billed monthly, according to its pricing page on November 7, 2026. Pro allows up to 10 members; Business starts at 3. Enterprise and Advanced Work Management are priced by quote. Both published plans list unlimited free contributors; check what a contributor can do before you decide who needs a paid seat.
For a team of six people who build and change schedules, the yearly cost works out as follows. The bold row is the cheapest option.
| Option | Per editor | 6 editors a year |
|---|---|---|
| Smartsheet Pro | $9 a month, yearly | $648 |
| Smartsheet Business | $19 a month, yearly | $1,368 |
| Wisegrid | $19 a month | $1,368 |
What this tells you: Smartsheet Pro is the cheapest way to run schedules for a small team, as long as you stay within 10 members and 250 automation runs a month. Business removes those caps and adds timeline view and unlimited automations. Wisegrid’s price was taken from its pricing page on the same day. For how Smartsheet counts members at renewal, see our posts on the Smartsheet user subscription model, Smartsheet pricing and the Smartsheet true-up.
What limits should you plan for?
Plan for the sheet size limits, the cross-sheet reference limit and, on Pro, the automation and dashboard caps. These figures come from Smartsheet’s developer documentation and pricing page.
| Limit | Standard | Large-scale |
|---|---|---|
| Rows per sheet | 20,000 | 100,000 |
| Columns per sheet | 400 | 400 |
| Cells per sheet | 500,000 | 1,000,000 |
| Cross-sheet references | 100 per sheet | 100 per sheet |
| Automation runs, Pro | 250 a month | Not on Pro |
Large-scale limits apply to Enterprise and Advanced Work Management; Business uses the standard limits. A single project schedule rarely reaches 20,000 rows, but logs that grow every day can, as covered in our post on the Smartsheet cell limit.
Common mistakes when running projects in Smartsheet
- Building the schedule before turning on dependencies. You end up retyping every date.
- Typing dates over predecessors. It silently breaks the link for that row.
- No baseline. Without one, nobody can show how far the finish date has moved since approval.
- One giant sheet for every project. Split by project and roll up with reports, within the 100 cross-sheet reference limit.
- Everyone as a paid member. People who only update their own rows may work as free contributors; check before renewal.
- Forgetting the exit plan. Exports lose formulas, automations and links; read what you lose when you export from Smartsheet before you need to.
When to keep Smartsheet and when to move
Keep Smartsheet if your schedules fit within its limits, your team uses Gantt, dependencies and dashboards every week, and the per-member cost is predictable at renewal. It is a mature product, and moving has a real cost in time.
Consider a move if renewals keep growing because more people need edit rights, if large logs hit the row or cell limits, or if your team only uses the grid. Wisegrid, a spreadsheet-native work management app, keeps the grid with dependencies, date-triggered automations and cross-sheet reporting, allows 1,000,000 cells per sheet and charges $19 per editor a month with free viewers. The migration guide and how to migrate off Smartsheet explain the move, Wisegrid vs Smartsheet compares the two directly, and before you renew Smartsheet lists the questions to ask first.
FAQ
Does Smartsheet have a project management template?
Yes. Smartsheet publishes a library of project management templates, and its project sheets come with the project columns already set up: task name, start and end dates, duration, predecessors, percent complete and assigned to. Starting from one saves the setup steps, but check that dependencies are turned on and that working days match your calendar before you enter dates.
How do I add dependencies in Smartsheet?
Turn on dependencies in Project Settings, or in sheet settings in the newer views, and map the Duration and Predecessors columns. Then type the row number of each predecessor, such as 3, or 3FS for finish-to-start. Smartsheet’s help lists this for Business and Enterprise plans, so confirm it on your plan.
Can Smartsheet show the critical path?
Yes. Once dependencies are on and each task has dates or a duration, select Show Critical Path in Gantt view and Smartsheet highlights the critical tasks in red. Only sheet owners and admins can turn on the dependencies that the critical path needs.
Is Smartsheet better than Microsoft Project?
They suit different teams. Smartsheet is easier to share and update in a browser, with free contributors and dashboards. Microsoft Project is a dedicated scheduling tool with deeper resource and scheduling features. Many teams schedule in one and report in another; the Microsoft Project dashboard template shows one way to bridge them.
How many rows can a Smartsheet project sheet have?
A standard sheet holds 20,000 rows, 400 columns and 500,000 cells. Enterprise and Advanced Work Management plans support large-scale sheets with 100,000 rows and 1,000,000 cells. Business plans use the standard limits.
Sources
- Smartsheet: Pricing (checked November 7, 2026)
- Smartsheet Developers: Limitations
- Smartsheet Help: Activate dependencies and use predecessors
- Smartsheet Help: Track a project’s critical path
- Smartsheet Help: Create and work with a Gantt view
- Smartsheet: Project management templates
- Wisegrid: Pricing (checked November 7, 2026)
Bring your Smartsheet schedule with you
Import a Smartsheet project into Wisegrid and keep the grid, the predecessors and the formulas. Then add a Gantt view, roll projects into the project dashboard, and compare costs with our Smartsheet alternatives guide.
Start free → · Wisegrid vs Smartsheet · Migration guide
About the author Ryan Kramer is the founder of Wisegrid, a higher-capacity work management grid built around a 1,000,000-cell-per-sheet limit, date-triggered automations with run history, and cross-sheet reporting. He writes about the project management documents teams actually keep updated. More from Ryan →