By Ryan Kramer, founder of Wisegrid. Last updated November 2026.
A construction bid template is a standard document a contractor fills in to offer a price for a job: who is bidding, what work is included and excluded, the base bid, any alternates, how long the price holds and how payment works. It turns your estimate into an offer the owner can compare with other bids.
Bids are lost on price, but money is lost on scope. A bid that does not say what is excluded invites the owner to assume everything is included. This guide lists what a construction bid should include, gives you the template sections, works through a $153,400 office renovation bid where every number adds up, and shows how to level subcontractor quotes so the lowest number really is the lowest price.
Key takeaways
– An estimate is your math; a bid is your offer. Keep markup in the estimate and send the owner a clear price, scope and terms.
– Exclusions protect your margin. Anything the bid does not exclude, the owner will read as included.
– Level subcontractor quotes before you use them. Add back what each quote leaves out, then compare.
– Alternates are separate prices. List each one as an add or a deduct so the owner can choose without a new bid.
– Public bids have extra rules. Bid bonds and bid forms are set by the owner and differ by state and agency.
What is a construction bid?
A construction bid is a contractor’s formal offer to do a defined scope of work for a stated price, usually in response to an owner’s invitation to bid or request for proposal. If the owner accepts it, the bid becomes the basis of the contract.
A bid is not the same as an estimate. The construction estimate is your internal calculation of cost, with quantities, unit costs and markup. The bid is the document you send: the price, the scope of work, what is excluded and the terms. On public work the owner often supplies its own bid form, and you must use it exactly.
What should a construction bid include?
Every bid needs the same eight sections, whatever the job size. The table lists them in the order the owner reads them.
| Section | What goes in it | Example |
|---|---|---|
| Bidder details | Company, license number, contact | License on file |
| Project details | Owner, address, bid date, documents | Drawings dated Oct 30 |
| Scope included | Work you will do, by trade | Interior renovation |
| Exclusions | Work you will not do | Furniture, data cabling |
| Base bid | One price for the scope | $153,400 |
| Alternates | Optional adds or deducts | Add $4,850 |
| Schedule | Start and duration | 10 weeks |
| Terms | Validity, payment, retainage | Valid 30 days |
List the drawings and addenda you priced, by date. If the owner issues a new drawing after you bid, that list is how you show the change is extra work, which becomes a change order rather than a free favor.
Worked example: a 2,400-square-foot office renovation bid
A small general contractor is bidding the interior renovation of a 2,400-square-foot office: new walls, lighting, flooring and a break room. It will self-perform demolition and hire subcontractors for the rest. The first table is the cost side of the estimate; the second turns cost into the base bid.
| Line | Source | Cost |
|---|---|---|
| Demolition | Own crew | $6,400 |
| Framing and drywall | Subcontract | $28,500 |
| Electrical | Leveled quote | $22,800 |
| Heating and cooling | Subcontract | $14,600 |
| Plumbing | Subcontract | $7,900 |
| Flooring | Subcontract | $16,300 |
| Painting | Subcontract | $8,200 |
| Doors and hardware | Supply and install | $9,700 |
| General conditions | Supervision, dumpster, permit | $10,600 |
| Total | $125,000 |
General conditions are the job costs that are not part of any one trade, such as the superintendent’s time, temporary protection, the dumpster and the permit. The bold electrical line comes from the leveling table further down.
| Step | Basis | Amount |
|---|---|---|
| Job cost | 9 lines | $125,000 |
| Contingency | 4% of job cost | $5,000 |
| Cost with contingency | $130,000 | |
| Overhead | 10% of $130,000 | $13,000 |
| Profit | 8% of $130,000 | $10,400 |
| Base bid | $153,400 |
What this tells you: overhead and profit add $23,400, an 18% markup on cost with contingency. As a share of the $153,400 price, that is a margin of about 15.3%. Confusing the two is one of the most common pricing errors; the construction estimate builder shows both as you type.
The bid also lists two alternates, so the owner can adjust scope without asking for a new price: Alternate 1, porcelain tile instead of vinyl plank in the break room, add $4,850; Alternate 2, leave the existing corridor unpainted, deduct $1,900. If the owner accepts both, the contract sum is $153,400 + $4,850 − $1,900 = $156,350.
How do you level subcontractor quotes?
You level subcontractor quotes by adding back anything a quote leaves out, so every quote covers the same scope before you compare them. The lowest number on paper is often not the lowest price.
| Electrician | Quote | Missing | Added | Leveled |
|---|---|---|---|---|
| Sub A | $21,900 | Fire alarm | $1,600 | $23,500 |
| Sub B | $22,800 | Nothing | $0 | $22,800 |
| Sub C | $20,400 | Fire alarm, permit | $2,700 | $23,100 |
What this tells you: Sub C looked $2,400 cheaper than Sub B, but once its gaps are priced it costs $300 more. The amounts added for missing scope are the contractor’s own estimates; ask the subcontractor to confirm them before you rely on them. Put the leveled number, not the quote, into your bid, and keep the leveling sheet with the bid file.
Watch: Job Costing for a Small Crew (2 minutes)
Watch “Job Costing for a Small Crew” on YouTube →
How to put a construction bid together, step by step
- Read the bid documents twice. Note the bid date, the required bid form, bonds, insurance limits and every addendum.
- Do the takeoff and self-performed pricing. Count quantities from the drawings and price your own crew’s work with a burdened labor rate.
- Send scopes to subcontractors early. Give each trade a written scope and the same drawing list, and ask for exclusions in writing.
- Level the quotes. Use the table above for every trade with more than one quote.
- Add general conditions, contingency, overhead and profit. Check the markup against your margin target.
- Write scope, exclusions and alternates. Use the owner’s wording for alternates so they match the bid form.
- State the terms. How long the price holds, the payment schedule, retainage and the drawings you priced.
- Review and submit on time. A second person checks the math and the form. On public work, a late bid can be rejected outright.
Once you win, keep the same lines. They become the schedule of values on your pay applications and the budget you track in job costing.
What about bid bonds on public jobs?
A bid bond is a guarantee from a surety company that you will sign the contract and provide any required bonds if you win. Public owners often require one; private owners sometimes do. The amount and form are set by the owner, so read the bid documents rather than assuming a number.
Two reference points help. On federal contracts, the Federal Acquisition Regulation says a bid guarantee must be at least 20% of the bid price, capped at $3 million, and federal construction contracts over $150,000 also need performance and payment bonds under the Miller Act. On private work, the American Institute of Architects (AIA) A310 Bid Bond form sets a maximum amount; if the winning bidder does not sign, the owner can recover the extra cost of awarding the job to the next bidder, up to that amount. State and local rules differ, and this is general information, not legal advice.
Common construction bid mistakes
- No exclusions. “Furniture, data cabling and signage by owner” in one line saves an argument later.
- Using a subcontractor’s quote without leveling it. The gap shows up on site, at your cost.
- Markup and margin mixed up. An 18% markup is a 15.3% margin, not 18%.
- No validity period. Material prices move; say how long the price holds.
- Pricing an old drawing set. Always list the drawings and addenda you priced.
- Forgetting general conditions. Supervision, cleanup and permits are real costs on every job.
- Ignoring the cash flow. Retainage and payment timing decide whether a winning bid also keeps you paid; see retainage in construction.
From a spreadsheet bid to a shared Wisegrid sheet
Most small contractors build bids in a spreadsheet, and that is a sensible place to do it. The problems start between bids: subcontractor quotes arrive by email, the leveling lives in someone’s copy, and the winning bid has to be retyped into the budget.
Wisegrid, a spreadsheet-native work management app, keeps the grid you already use. One sheet holds the bid lines, a linked sheet holds the subcontractor quotes with dropdowns for status, and when the job is won the same rows become the job budget, with no retyping. Start from the free estimate template or quote template, then move the won job into the job costing template. If you only bid a few jobs a year, a well-built spreadsheet may be all you need.
FAQ
What is the difference between a bid and an estimate?
An estimate is the contractor’s internal calculation of what a job will cost, with quantities, unit costs and markup. A bid is the offer sent to the owner: the price, scope, exclusions and terms. Many small contractors send a cleaned-up estimate as the bid, which works as long as internal notes, such as markup percentages, are removed.
How do you bid a construction job for the first time?
Start with a job you understand well. Read every bid document, measure quantities from the drawings, get at least two written quotes per trade, level them, and add general conditions, contingency, overhead and profit. Write clear exclusions. Then ask an experienced contractor or estimator to review the bid before you submit it.
How much profit should I put in a construction bid?
There is no single right number; it depends on your overhead, risk and market. What matters is that overhead and profit are calculated, not guessed. Work out your yearly overhead as a share of revenue, add the profit you need, and remember that markup on cost is always a bigger percentage than the margin it produces.
What are alternates in a construction bid?
Alternates are separate prices for optional changes to the base scope, written as an add or a deduct. The owner asks for them so it can adjust scope to its budget without rebidding. Price each one on its own and say whether it depends on another alternate being accepted.
How long is a construction bid valid?
As long as the bid says. Public bid documents usually set the period, and the bidder cannot change it. On private work, state it yourself, for example 30 days, so a delayed decision does not lock you into a price after material costs have changed.
Sources
- Federal Acquisition Regulation 28.101-2: Solicitation provision or contract clause (bid guarantee)
- Federal Acquisition Regulation 28.102-1: Performance and payment bonds, general
- AIA Contract Documents: Summary of A310–2010, Bid Bond
Bid it, win it, track it in one grid
Build your next bid on the free estimate template, price it with the construction estimate builder, and when you win, carry the same lines into a draw schedule so billing starts on day one.
Start free → · Quote template · Job costing template
About the author Ryan Kramer is the founder of Wisegrid, a higher-capacity work management grid built around a 1,000,000-cell-per-sheet limit, date-triggered automations with run history, and cross-sheet reporting. He writes about the project management documents teams actually keep updated. More from Ryan →