By Ryan Kramer, founder of Wisegrid. Last updated November 2026.
The AIA G702 is the American Institute of Architects (AIA) form a contractor uses to request a progress payment. Its full name is the Application and Certificate for Payment. It is a one-page summary of the contract sum, change orders, work done to date, retainage and the amount due now. The line-by-line detail sits on its companion form, the G703 continuation sheet.
Owners, architects and lenders review a lot of payment applications. A G702 that adds up, matches the G703 and shows change orders clearly gets certified quickly. One that does not is sent back, and you wait another month. This guide explains every line of the G702, works through a filled-in example, and lists the checks to run before you send it.
Key takeaways
– The G702 is the summary; the G703 is the detail. Every total on the G702 comes from a column on the G703.
– Nine numbered lines lead to one number: line 8, the current payment due.
– Retainage is split on line 5 between completed work and stored materials, which can have different rates.
– Line 7 must match what was certified last time, not what you asked for.
– The architect can certify less than you applied for and must initial every changed figure.
What is the AIA G702?
The G702 is used on projects that follow AIA contracts, and many owners and lenders ask for it on other projects too. The contractor fills it in, signs it and, on the standard form, has it notarized. The architect reviews it, checks the work on site, and signs the Architect’s Certificate for Payment for the amount they agree is due. The owner then pays the certified amount.
The current edition is G702–1992. It has stayed the same for decades, which is why so many owners, banks and accounting systems expect it. Subcontractors often use the same form to bill the general contractor.
How do the G702 and G703 work together?
The G703 continuation sheet lists every line of the schedule of values with billing columns. You fill in the G703 first, then carry its totals to the G702. These are the G703 columns:
| G703 column | What it holds |
|---|---|
| A. Item number | Line number |
| B. Description of work | What the line covers |
| C. Scheduled value | Dollar value of the line |
| D. From previous application | Work billed before (D + E last time) |
| E. This period | Work done since the last application |
| F. Materials presently stored | Delivered, not yet installed |
| G. Completed and stored | D + E + F |
| G ÷ C | Percent complete |
| H. Balance to finish | C − G |
| I. Retainage | Retainage held, if rates vary |
Column G’s total becomes line 4 on the G702. Columns D + E feed line 5a, and column F feeds line 5b.
AIA G702 example, line by line
A $480,000 interior fit-out, payment application number 4. Two change orders were approved this month: one adds $14,000 and one is a $1,600 credit. Retainage is 10% on completed work and on stored materials. Of the $286,000 completed and stored to date, $268,000 is completed work and $18,000 is materials stored on site. The bold row is the amount the contractor asks to be paid.
| G702 line | What it means | Amount |
|---|---|---|
| 1. Original contract sum | Price in the signed contract | $480,000 |
| 2. Net change orders | Approved additions minus credits | $12,400 |
| 3. Contract sum to date | Line 1 + line 2 | $492,400 |
| 4. Completed and stored | Total of G703 column G | $286,000 |
| 5a. Retainage on work | 10% of $268,000 | $26,800 |
| 5b. Retainage on stored | 10% of $18,000 | $1,800 |
| 5. Total retainage | 5a + 5b | $28,600 |
| 6. Earned less retainage | Line 4 − line 5 | $257,400 |
| 7. Previous certificates | Line 6 from the last certificate | $206,505 |
| 8. Current payment due | Line 6 − line 7 | $50,895 |
| 9. Balance to finish | Line 3 − line 6, incl. retainage | $235,000 |
What this tells you: the contractor billed $56,550 of new work this period ($286,000 − $229,450 billed through application 3). Ninety percent of that is $50,895, which matches line 8. That second calculation is the quickest way to catch a typo before the architect does. The $206,505 on line 7 is the earned-less-retainage figure from application 3, shown in our schedule of values example.
The change order summary
The box on the left of the G702 shows how line 2 was built. Additions and deductions are kept separate, so the owner can see each direction:
| Change orders | Additions | Deductions |
|---|---|---|
| Approved in previous months | $0 | $0 |
| Approved this month | $14,000 | $1,600 |
| Total | $14,000 | $1,600 |
| Net change by change orders | $12,400 |
Only approved change orders belong here. Pending changes stay off the G702 until they are signed. Each approved change order should also appear as its own line on the G703. Our change order template and process guide covers how to get them signed in time for the next application.
How to fill out a G702, step by step
- Start from the last certified application, not the last one you sent. If the architect changed figures, use theirs.
- Update the G703. Enter work done this period and materials stored on each line, based on a site walk with the superintendent. Our guide on how to inspect construction work covers what to check.
- Add newly approved change orders as new G703 lines and in the change order summary.
- Carry the totals to the G702. Column G to line 4, then work through lines 5 to 9.
- Check line 8 two ways: line 6 minus line 7, and new work this period minus its retainage.
- Attach what the owner requires. Often lien waivers from you and your subcontractors, invoices for stored materials and proof of insurance for stored items.
- Sign, notarize if required, and send by the contract deadline. Many contracts set a fixed day of the month. Miss it and you wait a month.
Common G702 mistakes that delay payment
- Line 7 copied from your last request instead of the last certificate. If the architect certified less last month, your line 8 will be too high.
- G702 totals that do not match the G703. Usually a line added to one form and not the other.
- Pending change orders included. They get removed, and the whole application is recalculated.
- Stored materials without backup. Owners and lenders often want an invoice, photos and proof that the materials are insured and secured.
- Front-loaded percent complete. Billing more than the work on site gets the line cut back and costs trust for the rest of the job.
- Wrong retainage rate. Check whether your contract or state law reduced retainage partway through the job. Our retainage guide covers how rates and caps work.
What happens after you submit?
The architect reviews the application against the work on site. If they agree, they sign the certificate for the amount applied for. If they do not, the AIA instructions allow them to certify a different amount, initial every figure they change on the G702 and G703, and attach an explanation. The owner then pays the certified amount within the time set in the contract. The final application, which releases retainage, usually waits until the construction punch list and closeout documents are done.
On jobs financed by a construction loan, the lender may also send an inspector before releasing funds. Lender draws on smaller jobs often follow milestones instead, as our construction draw schedule guide explains.
From spreadsheet to a shared pay application
Many contractors build the G703 in Excel and type the totals into the G702 by hand. It works until someone forgets to roll this period into “from previous application,” a change order is added to one tab but not the other, or the retainage formula breaks when a row is inserted.
In Wisegrid, the schedule of values is one shared sheet, with each billing period kept as a set of columns. Previous-application amounts carry forward, change orders are added as new rows, and the G702 summary is a set of formulas you can check line by line. The same lines feed your construction job costing, so you can compare what you billed with what you spent. The owner and lender can view it for free. You still send the official AIA form; the sheet just makes sure the numbers on it are right. Start from the construction job costing template and track the job on the construction project dashboard.
FAQ
What is the difference between the G702 and G703?
The G702 is the one-page summary with the contract sum, retainage, previous payments and current payment due. The G703 is the continuation sheet that lists every schedule of values line with its billing columns. You fill in the G703 first and carry its totals to the G702.
Does the G702 have to be notarized?
The standard G702 has a notary section in the contractor’s certification. Whether you must use it depends on your contract and the owner’s or lender’s requirements. Some owners waive it, especially with electronic signatures. Ask at the start of the job so the first application is not returned.
Can I use the G702 if my contract is not an AIA contract?
Many owners and lenders accept or even ask for the G702 and G703 on other contracts, because the format is familiar. Use whatever form your contract names. If it names none, agree a format with the owner before the first payment application.
Who signs the architect’s certificate for payment?
The architect named in the contract signs it after reviewing the application and the work on site. On projects without an architect, the owner or the owner’s representative usually approves the payment instead.
Is there a free G702 template?
The official form is sold by AIA Contract Documents. Many contractors build the calculations in a spreadsheet using the nine lines and the G703 columns above, then transfer the figures to the official form. The free construction estimate builder can help set up the schedule of values lines to start from.
Sources
- AIA Contract Documents: Instructions for G702–1992, Application and Certificate for Payment
- AIA Contract Documents: How to complete the G702 payment application
- AIA Contract Documents: Summary of G703–1992, Continuation Sheet
Get the pay application right before you send it
Keep the schedule of values, change orders and job costs on one shared Wisegrid sheet. Start with the construction job costing template, log approvals in the change order log, and plan lender draws with the draw schedule template.
Start free → · Schedule of values guide → · Retainage guide →
About the author Ryan Kramer is the founder of Wisegrid, a higher-capacity work management grid built around a 1,000,000-cell-per-sheet limit, date-triggered automations with run history, and cross-sheet reporting. He writes about the project management documents teams actually keep updated. More from Ryan →