By Ryan Kramer, founder of Wisegrid. Last updated November 2026.
A request for information (RFI) in construction is a written question from the contractor to the architect or engineer about the drawings or specifications. It is used when something is missing, unclear or in conflict, and the crew cannot build it without an answer. Each RFI gets a number, a due date and a written response, and every RFI on a job is tracked in an RFI log.
RFIs look like paperwork, but late answers stop crews and late questions lead to rework. A clear RFI with a suggested answer gets a fast reply. A vague one sits on someone’s desk. This guide covers what an RFI is for, what to put in it, a worked RFI log, the process from question to answer, and how RFIs turn into change orders.
Key takeaways
– An RFI asks a question about the design. It does not approve extra cost or time by itself.
– Good RFIs point to a drawing or specification and suggest an answer, so the designer only has to say yes or adjust it.
– Every RFI gets a number and a due date in one log that everyone can see.
– Late RFIs are schedule risks. Check the log every week and chase anything past due.
– If the answer changes cost or time, follow it with a change order. The RFI answer is not enough.
What is an RFI in construction?
An RFI is how the people building a project ask the people who designed it to explain something. Common reasons include a dimension that does not match between two drawings, a product that is no longer made, a detail that is missing, or a pipe that runs through a beam. The question usually goes from a subcontractor to the general contractor, and from the general contractor to the architect or engineer.
Being able to read the drawings well cuts down RFIs, because many questions are answered elsewhere in the set. Our guide on how to read construction blueprints covers where to look first. The American Institute of Architects (AIA) publishes a standard form, G716, and notes that the requester should name the drawing, specification or submittal it already checked.
RFI vs submittal vs change order
These three documents are often confused. Here is the short version:
| Document | What it does |
|---|---|
| RFI | Asks a question about the design |
| Submittal | Shows the product or shop drawing to approve |
| Change order | Changes the contract price or time |
Submittals have their own log, covered in our construction submittal log guide. Change orders are covered in our change order template and process guide.
What goes in an RFI?
Keep each RFI to one question. Two questions in one RFI usually get one answer. Include these fields:
| Field | What to write |
|---|---|
| RFI number | RFI-016, numbered in order |
| Date sent | The day it went out |
| From and to | Who asks, who must answer |
| Reference | Drawing, detail or spec section |
| Question | One clear question |
| Suggested answer | What you propose to do |
| Response needed by | Date the crew needs it |
| Possible impact | Cost, time, or none |
| Response | The answer, who gave it, date |
The suggested answer is the most useful field. “Can we move the duct 8 inches west to clear the sprinkler main?” gets a faster reply than “Duct conflicts with sprinkler. Please advise.” Add a marked-up drawing or a photo whenever you can.
RFI log example
A three-story office building. Today is March 12. The log shows the five most recent RFIs. Due back is the date the answer was promised. Bold rows are late.
| RFI | Question | Sent | Due back | Status |
|---|---|---|---|---|
| RFI-014 | Beam size at grid C-4 | Feb 24 | Mar 3 | Answered |
| RFI-015 | Door hardware for room 210 | Feb 27 | Mar 6 | Late, 6 days |
| RFI-016 | Duct hits sprinkler main | Mar 2 | Mar 9 | Late, 3 days |
| RFI-017 | Lobby floor finish missing | Mar 5 | Mar 12 | Due today |
| RFI-018 | Window rough opening size | Mar 10 | Mar 17 | Open |
What this tells you: two RFIs are late, and they are not equal. RFI-016 blocks the corridor ceiling, which holds up drywall on the whole floor and pushes the project schedule. RFI-015 matters only when doors are ordered. Chase RFI-016 first, by phone, and mark it in the weekly owner–architect–contractor meeting.
Add two more columns to a real log: Ball in court, meaning who must act next, and Cost or time impact. A days-open formula, today minus the date sent, makes old RFIs stand out without anyone counting by hand.
The RFI process, step by step
- Check the documents first. Search the drawings, specifications, addenda and approved submittals. Many RFIs are answered somewhere in the set.
- Write one question with a reference and a suggested answer. Attach a sketch or photo.
- Set a response date based on when the crew needs the answer, within the time your contract allows. If the contract sets no time, agree one at the start of the job.
- Log it the day it is sent and send it to the right person. Subcontractor RFIs should go through the general contractor so nothing is answered twice.
- Review the log weekly and call about anything late. Late RFIs that affect the schedule should be noted in writing, for example as issues in a RAID log (risks, assumptions, issues and dependencies).
- Close it with the written answer and share it with every trade it affects. Update the drawings on site so the old detail is not built by mistake.
- If the answer changes cost or time, start a change order the same day.
When does an RFI become a change order?
When the answer asks for work that is not in the contract. In the log above, if the engineer answers RFI-016 by asking the mechanical subcontractor to reroute the duct with extra fittings, that is new work. The AIA notes on its G716 form that neither the request nor the response authorizes extra cost or time. You still need a change order.
Price it, log it in the change order log template, and get it signed before the extra work is done. Note the RFI number on the change order so the reason is clear later. If the issue could affect the schedule or budget more widely, add it to the project’s risk register too.
Common RFI mistakes
- Asking what the drawings already answer. It slows the real questions and annoys the design team. Some contracts allow the architect to charge for it.
- Several questions in one RFI. Split them so each one can be answered and closed.
- No suggested answer. The designer has to start from zero, and the reply takes longer.
- No due date, or every RFI marked urgent. If everything is urgent, nothing is.
- Answers that never reach the field. The RFI is closed in the office, and the crew builds from the old drawing. Check RFI answers during your construction inspections.
- Treating the RFI answer as approval for extra money. Without a change order, the extra work may never be paid.
From spreadsheet to a shared RFI log
Many contractors start with an RFI log in Excel, and the columns above are the whole template. It gets harder when the log lives on the project manager’s laptop, subcontractors email questions that never make it in, and the architect cannot see which RFIs the contractor thinks are late.
In Wisegrid, the RFI log is one shared sheet for the job. Subcontractors can add their questions, the architect sees what is due, days open is calculated for everyone, and late RFIs show up on the construction project dashboard next to submittals and change orders. Wisegrid does not have a dedicated RFI template yet, so copy the columns from this post into a new sheet. For other job documents, see our construction project management templates, and for the end of the job, the construction punch list guide.
FAQ
Who answers an RFI?
Usually the architect, who passes structural, mechanical or electrical questions to the engineer responsible. Some questions go to the owner, such as finish choices. The general contractor collects the answer and shares it with the subcontractors who asked.
How long should an RFI response take?
As long as your contract allows. Many contracts set a response time, and some only say the architect must answer with reasonable promptness. Agree a standard time at the start of the job, and set each RFI’s due date by when the work actually needs the answer.
Does an RFI change the contract price?
No. An RFI and its answer do not change the contract price or schedule by themselves. If the answer requires extra work or time, the contractor should request a change order and get it signed before doing the work.
What is an RFI log?
A list of every RFI on a project with its number, question, dates, status and answer. It shows which questions are open and late, and it is the record if there is later a dispute about delays or extra cost.
How many RFIs are normal on a project?
It depends on the size of the job, how complete the drawings are and the delivery method. A large, fast-tracked building will have far more than a small renovation. Rather than a target number, watch for patterns, such as many RFIs on the same drawing, which point to a design gap worth a meeting.
Sources
- AIA Contract Documents: Summary of G716–2004, Request for Information
- SMACNA: Making RFIs More Effective
Keep RFIs, submittals and changes in one place
Track RFIs on a shared Wisegrid sheet next to the job’s other logs. Start with the change order log template, see every open item on the construction project dashboard, and report weekly with the executive project status report template.
Start free → · Submittal log guide → · Construction templates →
About the author Ryan Kramer is the founder of Wisegrid, a higher-capacity work management grid built around a 1,000,000-cell-per-sheet limit, date-triggered automations with run history, and cross-sheet reporting. He writes about the project management documents teams actually keep updated. More from Ryan →