Change Orders in Construction: Template, Log and Process (2026)

A construction change order template, a change order log with totals, how to price extra work with markup, and the 6-step process that gets it paid.

By Ryan Kramer, founder of Wisegrid. Last updated November 2026.

A change order is a written agreement that changes a construction contract after it is signed. It records what work is added or removed, what it costs, and how many days it adds. The owner and contractor both sign it before the work is done. A change order log lists every change order on a job, so you can see the revised contract at a glance.

Extra work that never becomes a signed change order is one of the most common ways small contractors lose money. The owner asks for something small, the crew does it, and nobody prices it. This guide gives you a change order template, a worked change order log, how to price extra work, and a six-step process that gets it billed.

Key takeaways

– No signature, no extra work. Get the change order signed before the crew starts, or get a written directive if it cannot wait.

– Price every change the same way. Labor, materials, subcontractors, then markup for overhead and profit, plus any days added.

– Keep one change order log per job. It shows approved, pending and rejected changes and the revised contract total.

– Credits are change orders too. Removed work and owner-supplied items reduce the contract and belong in the log.

– Bill approved changes as new lines on your next payment request. Do not change the original contract lines.

What is a change order in construction?

A change order is a written change to the contract’s scope, price, time or all three. It can add work, remove work (a credit), or change how something is built. On projects using American Institute of Architects (AIA) contracts, changes are covered in Article 7 of the A201 General Conditions, and the standard change order form is AIA G701, signed by the owner, architect and contractor.

Change orders usually come from three places: the owner asks for something new, the crew finds a hidden condition such as rot or old wiring, or the drawings have an error or gap. Whatever the cause, the written scope of work is the baseline. Anything outside it is a change.

Change order vs construction change directive

A construction change directive is a written order from the owner to go ahead with a change before the price or time is agreed. On AIA projects it uses form G714. It keeps urgent work moving, such as a code fix the inspector requires. Once the price is settled, it is turned into a regular change order. Very small changes that do not affect price or time are often handled as a minor change in the field.

What goes in a change order template?

A good change order fits on one page. These are the fields to include, whether you use the AIA form, the free change order template or your own:

Field What to write
Change order number CO-05, numbered in order
Date and requester Who asked for it, and when
Description What changes, in plain words
Reason Owner request, hidden condition, design error
Cost breakdown Labor, materials, subcontractors, markup
Schedule impact Days added, or “none”
Contract totals Original, approved to date, new total
Signatures Owner and contractor, with dates

The contract totals line is the one most templates leave out. It shows the owner the running effect of every change, which heads off arguments at the final invoice. The free change order generator fills these fields in for you.

How do you price a change order?

Price each change from its parts, then add markup for overhead and profit. Here is change order 5 from the log below: adding a skylight to a kitchen remodel. The markup rate is an example; use the rate in your contract.

Skylight change order Amount
Labor (28 hours × $70) $1,960
Skylight and flashing $2,640
Roofing subcontractor $1,000
Subtotal $5,600
Overhead and profit (15%) $840
Change order total $6,440

What this tells you: the direct cost is $5,600, and the markup is what pays for supervision, insurance, the office and profit. Many contracts set the markup rate, and some set different rates for your own work and for subcontractor work. Use a loaded labor rate, meaning wages plus taxes and benefits. The free labor cost calculator works it out. Add the 3 days the skylight adds to the schedule on the form too.

Watch: Stop Eating Change Orders (the one-sheet fix) (2 minutes)

Watch “Stop Eating Change Orders (the one-sheet fix)” on YouTube →

Change order log example

A $250,000 kitchen and bathroom remodel. The log has one row per change order. Bold rows are pending, which means priced and sent but not yet signed. Credits are shown as negative amounts.

Change order Description Amount Days Status
CO-01 Extra kitchen outlets $1,850 0 Approved
CO-02 Rot repair at back wall $4,200 2 Approved
CO-03 Upgrade to quartz counters $3,600 0 Approved
CO-04 Owner-supplied fixtures −$900 0 Approved
CO-05 Add kitchen skylight $6,440 3 Pending
CO-06 Move bathroom door $1,150 1 Pending

The log feeds a short contract summary. The approved total is $1,850 + $4,200 + $3,600 − $900 = $8,750.

Contract summary Amount
Original contract $250,000
Approved change orders $8,750
Revised contract $258,750
Pending change orders $7,590
If all pending are approved $266,340

What this tells you: approved changes have already added 3.5% to the job and 2 days to the schedule. Another $7,590 and 4 days are waiting on the owner. Do not start the skylight or the door until they are signed. The free change order log template has these columns and totals built in.

The change order process, step by step

  1. Stop and write it down. When the owner asks for something or the crew finds a problem, record it the same day, with photos if it is a hidden condition.
  2. Price it. Labor, materials, subcontractors, markup and days added, using the method above.
  3. Get it signed before the work starts. If the work cannot wait, get a written directive or at least an email approval, then follow with the formal change order.
  4. Add it to the change order log. Update the status the day it is signed or rejected.
  5. Update the budget and the schedule. Add the change as a new line in your construction job costing sheet so cost and price stay matched.
  6. Bill it on the next payment request. Add each approved change order as a new line on the schedule of values. Retainage usually applies to it too, as the retainage guide explains.

Common change order mistakes

  • Doing the work on a handshake. Weeks later, the owner remembers it as a favor. Verbal approvals are the hardest money to collect.
  • Forgetting the time. A change that adds three days but is signed with “0 days” can leave you liable for a late finish.
  • No markup. Billing a change at cost means you did extra work for free and paid for the supervision yourself.
  • Missing credits. Owners notice removed work that was never credited, and it costs trust.
  • Bundling changes at the end of the job. A $9,000 surprise on the final invoice starts an argument. Five signed changes of $1,800 do not.
  • Not passing changes to subcontractors. If the change affects their work, issue them a matching change to their subcontract.

From spreadsheet to a shared change order log

A spreadsheet change order log works when one person keeps it. Problems start when the superintendent agrees to a change on site, the project manager prices it in email, and the bookkeeper bills from an old copy. The log is only as current as the last person who remembered to update it.

In Wisegrid, the change order log is a shared sheet. The superintendent adds a row from the job site, the status moves from Pending to Approved when it is signed, and approved amounts feed the job costing template and the construction project dashboard automatically. Owners can view the log for free, so there are fewer surprises at the final invoice. For the other documents on a job, see our construction project management templates.

FAQ

Who signs a change order?

The owner and the contractor, at a minimum. On projects using AIA contracts the architect signs too, on form G701. A subcontractor’s change is signed by the subcontractor and the general contractor. Check your contract for who is allowed to approve changes and up to what amount.

What is a reasonable markup on a change order?

It depends on your contract and your market. Many contracts set the rate for overhead and profit, sometimes with a lower rate on subcontractor work. If the contract is silent, use the same markup you used in your original bid, and show it as a separate line so the owner can see it.

Can you do extra work without a signed change order?

You can, but you risk not being paid. Many contracts say the contractor is not owed for changed work done without written approval. If work truly cannot wait, get a written directive or email approval first, then the formal change order.

What is a deductive change order?

A change order that lowers the contract price, also called a credit. Removing work, using owner-supplied materials or downgrading a finish all produce deductive change orders. Log them like any other change, with a negative amount.

Is there a free change order template?

Yes. The Wisegrid change order template covers a single change, and the change order log template tracks every change on a job with running totals. Both work in Excel, Google Sheets or Wisegrid.

Sources


Get every change signed, logged and billed

Price changes with the change order template, track them in the change order log template, and see the effect on profit in the construction job costing template.

Start free → · Change order log → · Change order generator →


About the author Ryan Kramer is the founder of Wisegrid, a higher-capacity work management grid built around a 1,000,000-cell-per-sheet limit, date-triggered automations with run history, and cross-sheet reporting. He writes about the project management documents teams actually keep updated. More from Ryan →