Markup vs Margin in Construction: Formulas, Chart and Examples (2026)

Markup vs margin for contractors: the formulas, a conversion chart, a worked job example with overhead, and how to set markup that hits your target profit.

By Ryan Kramer, founder of Wisegrid. Last updated November 2026.

Markup and margin both describe profit, but they measure it against different numbers. Markup is profit as a percentage of cost. Margin is profit as a percentage of the selling price. A 20% markup on a construction job is only a 16.7% margin. Mixing the two up is one of the simplest ways a contractor underprices work.

Most contractors price jobs by marking up cost, but they think about profit as a share of revenue. The gap between those two views is real money on every job. This guide gives the formulas in plain words, a conversion chart, a worked example that includes overhead, and a simple way to set the markup that hits the profit you want.

Key takeaways

– Markup = profit ÷ cost. Margin = profit ÷ price. Same dollars, different bases.

– Margin is always lower than markup. A 25% markup gives a 20% margin.

– To hit a target margin, divide cost by (1 − margin). $100,000 ÷ 0.80 = $125,000 for a 20% margin.

– Overhead comes out of margin. If overhead is 10% of revenue, a 20% margin leaves 10% net profit.

– Use the same markup method on change orders so extra work earns the same as the base job.

What is the difference between markup and margin?

Take a job that costs $100,000 to build and sells for $125,000. The profit is $25,000 either way. Markup compares the $25,000 with the $100,000 cost: 25%. Margin compares it with the $125,000 price: 20%. Both are correct. They just answer different questions.

Measure Formula Example
Markup Profit ÷ cost $25,000 ÷ $100,000 = 25%
Margin Profit ÷ price $25,000 ÷ $125,000 = 20%
Price from markup Cost × (1 + markup) $100,000 × 1.25
Price from margin Cost ÷ (1 − margin) $100,000 ÷ 0.80

Contractors usually estimate with markup, because they build the price up from costs. Accountants and lenders report with margin, because financial statements start from revenue. Know which one you are looking at.

Markup to margin conversion chart

Use this chart to translate between the two. Margin = markup ÷ (1 + markup). The bold row is the example used in this guide.

Markup Margin
10% 9.1%
15% 13.0%
20% 16.7%
25% 20.0%
30% 23.1%
42.9% 30.0%
50% 33.3%

To go the other way, markup = margin ÷ (1 − margin). A 30% target margin needs a 42.9% markup, which surprises many contractors the first time they see it.

Worked example: pricing a job with overhead

A remodeler estimates a job at $100,000 in direct cost: labor, materials, subcontractors, permits and equipment for that job. The business’s overhead, meaning the office, trucks, insurance and salaries not tied to one job, runs at 10% of revenue. The owner wants 10% net profit. That means the job needs a 20% margin, which is a 25% markup.

Pricing the job Amount
Direct job cost $100,000
Markup (25%) $25,000
Price $125,000
Overhead (10% of price) $12,500
Net profit $12,500

Now the common mistake. The owner wants “20%” and adds a 20% markup, thinking it is a 20% margin.

Pricing method Price Gross margin Net profit
25% markup $125,000 20.0% $12,500
20% markup $120,000 16.7% $8,000

What this tells you: using markup and margin as if they were the same costs $4,500 on this one job, more than a third of the planned profit. Overhead on the $120,000 price is $12,000, so net profit falls to $8,000, or 6.7%. Over a year of similar jobs, that is the difference between a good year and a thin one.

Watch: Job Costing for a Small Crew (2 minutes)

Watch “Job Costing for a Small Crew” on YouTube →

How to set your markup, step by step

  1. Work out your overhead rate. Last year’s overhead ÷ last year’s revenue. For example, $180,000 ÷ $1,500,000 = 12%.
  2. Pick a net profit target, such as 8% or 10% of revenue.
  3. Add them to get your target margin. 12% + 10% = 22%.
  4. Convert to markup. 0.22 ÷ 0.78 = 28.2%. Round up, not down.
  5. Apply it to complete direct costs. Use a loaded labor rate, meaning wages plus payroll taxes, insurance and benefits. The free labor cost calculator works it out, and the construction estimate builder helps you list every cost.
  6. Check actual margin when the job closes. Your construction job costing sheet shows whether the job earned what the estimate promised.

Many contractors use different markups for their own labor, materials and subcontractors. That is fine, as long as the blended result still reaches your target margin. Check the total, not just each line.

Markup on change orders

Extra work should earn at least the same margin as the base job, since it uses the same office, supervision and insurance. Many contracts set the markup on change orders. In our change order template and process guide, a skylight with $5,600 of direct cost and a 15% markup is priced at $6,440. That is a margin of 13.0%, lower than the 20% on the base job in this example. If the contract sets 15%, that is the number. If it does not, use your normal markup and show it on its own line of the change order template.

Watch: Stop Eating Change Orders (the one-sheet fix) (2 minutes)

Watch “Stop Eating Change Orders (the one-sheet fix)” on YouTube →

Common markup and margin mistakes

  • Using markup and margin as the same number. The example above shows what it costs.
  • Leaving costs out of the estimate. Markup on an incomplete cost is still too low. Dumpsters, permits, cleanup and supervision are the usual gaps.
  • Forgetting the owner’s own time. If you run the job, your hours are a cost.
  • One overhead rate forever. Recalculate it every year, and when you add a truck, an office or a salaried person.
  • Never checking the result. Compare estimated margin with actual margin on every closed job. The free cost variance calculator helps line by line.
  • Ignoring cash timing. A healthy margin can still leave you short while retainage and draws are unpaid. See our construction cash flow forecast guide.

From spreadsheet to live margins

An estimating spreadsheet usually has the markup formula built in. The problem is what happens after the job is won. The estimate stays in one file, actual costs land in another, and nobody compares the margin you priced with the margin you are earning until the job closes.

In Wisegrid, the estimate becomes the job’s budget on the same sheet, actual and committed costs fill in as the job runs, and projected margin updates every week. Change orders carry your markup as their own line, and every job’s margin rolls up to the construction project dashboard. Start with the construction job costing template or set one up in minutes with the free job costing builder.

FAQ

Is a 20% markup the same as a 20% margin?

No. A 20% markup on cost gives a 16.7% margin on price. To get a 20% margin you need a 25% markup. Margin is always the smaller number, because it divides the same profit by the larger selling price.

What is a typical markup for a contractor?

It varies widely by trade, job size, region and how much overhead the business carries. Rather than copying an industry number, work out your own overhead rate, add the net profit you need, and convert that target margin to a markup using the formula in this guide.

How do I convert margin to markup?

Divide the margin by one minus the margin. For a 25% margin: 0.25 ÷ 0.75 = 33.3% markup. To convert markup to margin, divide the markup by one plus the markup.

Should overhead be included in job cost or in markup?

Either works if you are consistent. Most small contractors keep job cost to direct costs only and cover overhead and profit in the markup. Larger contractors sometimes add a share of overhead to each job’s cost first. What matters is that overhead is covered somewhere, every time.

What is the difference between gross margin and net margin?

Gross margin is price minus direct job cost, as a share of price. Net margin also subtracts overhead. In the example, gross margin is 20% and net margin is 10%.

Sources


Price the job, then watch the margin

Build the estimate, track real costs and see projected margin in one shared Wisegrid sheet. Start with the construction job costing template, price extra work with the change order template, and set budgets with the project budget template.

Start free → · Job costing builder → · Change order guide →


About the author Ryan Kramer is the founder of Wisegrid, a higher-capacity work management grid built around a 1,000,000-cell-per-sheet limit, date-triggered automations with run history, and cross-sheet reporting. He writes about the project management documents teams actually keep updated. More from Ryan →