{"id":230,"date":"2026-11-13T09:31:39","date_gmt":"2026-11-13T09:31:39","guid":{"rendered":"https:\/\/wisegrid.co\/blog\/?p=230"},"modified":"2026-11-10T09:32:25","modified_gmt":"2026-11-10T09:32:25","slug":"shop-drawings","status":"publish","type":"post","link":"https:\/\/wisegrid.co\/blog\/shop-drawings\/","title":{"rendered":"Shop Drawings in Construction: What They Are, How They Differ From Submittals, and How to Track Them"},"content":{"rendered":"<p><em>By <a href=\"\/blog\/author\/ryan-kramer\/\">Ryan Kramer<\/a>, founder of Wisegrid. Last updated November 2026.<\/em><\/p>\n<p><strong>Shop drawings<\/strong> are detailed drawings, diagrams and schedules that a contractor, subcontractor, fabricator or supplier prepares to show exactly how a part of the work will be made and installed. The architect or engineer reviews them against the design before anything is fabricated, but they are not part of the contract documents.<\/p>\n<p>Shop drawings matter because they sit on the critical path of most jobs: steel, storefronts, stairs, ductwork and sprinklers cannot be fabricated until their drawings come back reviewed. A late or rejected shop drawing becomes a late delivery weeks later. This guide explains what shop drawings are, how they differ from design drawings and other submittals, who prepares and reviews them, a worked shop drawing log, and how to plan backward from the install date so reviews never hold up the site.<\/p>\n<blockquote>\n<p style=\"margin:0\"><strong>Key takeaways<\/strong><\/p>\n<p style=\"margin:0.55em 0 0\">\u2013 <strong>Shop drawings show how the work will be built.<\/strong> Design drawings show what is wanted; shop drawings show the fabricator\u2019s exact sizes, connections and layout.<\/p>\n<p style=\"margin:0.55em 0 0\">\u2013 <strong>They are a type of submittal.<\/strong> Submittals also include product data and samples.<\/p>\n<p style=\"margin:0.55em 0 0\">\u2013 <strong>They are not contract documents.<\/strong> Under AIA A201, approval does not change the contract unless a change is issued.<\/p>\n<p style=\"margin:0.55em 0 0\">\u2013 <strong>The contractor reviews first.<\/strong> Check every shop drawing against the drawings and specifications before it goes to the architect.<\/p>\n<p style=\"margin:0.55em 0 0\">\u2013 <strong>Plan backward from the install date.<\/strong> Preparation, review, one resubmittal and fabrication time decide when each drawing must be submitted.<\/p>\n<\/blockquote>\n<nav class=\"wg-toc\" aria-label=\"Table of contents\">\n<div class=\"wg-toc-eyebrow\"><span class=\"lp-dot\" aria-hidden=\"true\"><\/span> On this page<\/div>\n<ul>\n<li><a href=\"#what-are\">What are shop drawings in construction?<\/a><\/li>\n<li><a href=\"#differences\">How are shop drawings different from design drawings and submittals?<\/a><\/li>\n<li><a href=\"#who\">Who prepares and who reviews shop drawings?<\/a><\/li>\n<li><a href=\"#log\">What does a shop drawing log look like?<\/a><\/li>\n<li><a href=\"#lead-time\">How far ahead should shop drawings be submitted?<\/a><\/li>\n<li><a href=\"#process\">How to manage shop drawings, step by step<\/a><\/li>\n<li><a href=\"#mistakes\">Common shop drawing mistakes<\/a><\/li>\n<li><a href=\"#spreadsheet-to-wisegrid\">Moving the shop drawing log from a spreadsheet to Wisegrid<\/a><\/li>\n<li><a href=\"#faq\">FAQ<\/a><\/li>\n<\/ul>\n<\/nav>\n<h2 id=\"what-are\">What are shop drawings in construction?<\/h2>\n<p>Shop drawings in construction are drawings prepared for the work by the contractor or a subcontractor, fabricator, manufacturer or supplier to show how a specific part of the work will be built. The American Institute of Architects (AIA) A201 General Conditions, section 3.12.1, defines them as \u201cdrawings, diagrams, schedules, and other data specially prepared for the Work by the Contractor\u201d or its subcontractors and suppliers.<\/p>\n<p>A typical shop drawing shows exact dimensions, member sizes, connection details, materials, finishes and how the item meets the surrounding work. Steel fabricators show every beam, bolt and weld; storefront suppliers show frame profiles and anchors; sheet metal contractors show duct routing and sizes. Section 3.12.4 of A201 says their purpose is \u201cto demonstrate how the Contractor proposes to conform to the information given\u201d in the contract documents.<\/p>\n<h2 id=\"differences\">How are shop drawings different from design drawings and submittals?<\/h2>\n<p>Design drawings show what the owner wants built, shop drawings show how the contractor will build it, and submittals are the wider family that shop drawings belong to. A201 lists three kinds of submittal in section 3.12: shop drawings, product data and samples. The table compares them with the design drawings.<\/p>\n<div class=\"wg-table-wrap\">\n<div class=\"wg-table-wrap\"><table>\n<thead>\n<tr>\n<th style=\"white-space:nowrap\">Document<\/th>\n<th style=\"white-space:nowrap\">Prepared\u00a0by<\/th>\n<th style=\"white-space:nowrap\">Shows<\/th>\n<th style=\"white-space:nowrap\">Example<\/th>\n<\/tr>\n<\/thead>\n<tbody>\n<tr>\n<td style=\"white-space:nowrap\"><strong>Design\u00a0drawings<\/strong><\/td>\n<td style=\"white-space:nowrap\">Architect\u00a0or\u00a0engineer<\/td>\n<td style=\"white-space:nowrap\">What\u00a0to\u00a0build<\/td>\n<td style=\"white-space:nowrap\">Floor\u00a0plan,\u00a0sections<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap\"><strong>Shop\u00a0drawings<\/strong><\/td>\n<td style=\"white-space:nowrap\">Contractor\u00a0or\u00a0fabricator<\/td>\n<td>How it will be made<\/td>\n<td style=\"white-space:nowrap\">Steel\u00a0connection\u00a0details<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap\"><strong>Product\u00a0data<\/strong><\/td>\n<td style=\"white-space:nowrap\">Manufacturer<\/td>\n<td style=\"white-space:nowrap\">Standard\u00a0product\u00a0info<\/td>\n<td style=\"white-space:nowrap\">Rooftop\u00a0unit\u00a0cut\u00a0sheet<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap\"><strong>Samples<\/strong><\/td>\n<td style=\"white-space:nowrap\">Supplier<\/td>\n<td style=\"white-space:nowrap\">Physical\u00a0example<\/td>\n<td style=\"white-space:nowrap\">Tile\u00a0or\u00a0paint\u00a0swatch<\/td>\n<\/tr>\n<\/tbody>\n<\/table><\/div>\n<\/div>\n<p>Because shop drawings are submittals, they move through the same log and review process as product data and samples. Our guide to the <a href=\"\/blog\/construction-submittal-log\/\">construction submittal log<\/a> covers the full process, and the post on <a href=\"\/blog\/what-is-a-construction-site-blueprint\/\">reading construction blueprints<\/a> explains the design drawings that shop drawings are checked against.<\/p>\n<h2 id=\"who\">Who prepares and who reviews shop drawings?<\/h2>\n<p>The subcontractor, fabricator or supplier usually prepares the shop drawings, the general contractor reviews and submits them, and the architect or engineer reviews them against the design. Responsibility for the drawings stays with the contractor, who controls the means and methods of construction and the coordination between trades.<\/p>\n<p>The design team\u2019s review is limited. Under AIA documents, the architect reviews submittals \u201cfor the limited purpose of checking for conformance with the project\u2019s design concept,\u201d not for the accuracy of every dimension. A201 section 3.12.4 also says shop drawings, product data and samples \u201care not Contract Documents.\u201d If an approved shop drawing shows something different from the contract, the contract does not change unless a change order is issued; see our guide to <a href=\"\/blog\/stop-eating-change-orders\/\">change orders<\/a>. When a shop drawing raises a question about the design, send a <a href=\"\/blog\/rfi-in-construction\/\">request for information (RFI)<\/a> instead of guessing on the drawing.<\/p>\n<h2 id=\"log\">What does a shop drawing log look like?<\/h2>\n<p>A shop drawing log is a list of every shop drawing on the job with its number, specification section, submission date, the date the review is due back and the current status. Here is the log for a three-story office building on January 22, 2027. The sample contract gives the architect 10 working days to review, so each item is due back 14 calendar days after it is submitted. Bold rows need action from the contractor.<\/p>\n<div class=\"wg-table-wrap\">\n<div class=\"wg-table-wrap\"><table>\n<thead>\n<tr>\n<th style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">No.<\/th>\n<th style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Item<\/th>\n<th style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Submitted<\/th>\n<th style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Due\u00a0back<\/th>\n<th style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Status<\/th>\n<\/tr>\n<\/thead>\n<tbody>\n<tr>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>SD-01<\/strong><\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Structural\u00a0steel\u00a0framing<\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Jan\u00a06<\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Jan\u00a020<\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Approved\u00a0as\u00a0noted<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>SD-02<\/strong><\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>Metal\u00a0stairs<\/strong><\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Jan\u00a011<\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Jan\u00a025<\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>Revise\u00a0and\u00a0resubmit<\/strong><\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>SD-03<\/strong><\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Aluminum\u00a0storefront<\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Jan\u00a04<\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Jan\u00a018<\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Approved<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>SD-04<\/strong><\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Hollow\u00a0metal\u00a0frames<\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Jan\u00a013<\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Jan\u00a027<\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">In\u00a0review<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>SD-05<\/strong><\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Metal\u00a0ductwork<\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Jan\u00a015<\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Jan\u00a029<\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">In\u00a0review<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>SD-06<\/strong><\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>Sprinkler\u00a0layout<\/strong><\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>Not\u00a0yet<\/strong><\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><\/td>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>4\u00a0days\u00a0late<\/strong><\/td>\n<\/tr>\n<\/tbody>\n<\/table><\/div>\n<\/div>\n<p><strong>What this tells you:<\/strong> the metal stairs came back early with comments and must be corrected and resubmitted, which restarts a 14-day review. The sprinkler layout was due on January 18 and has not been submitted, so the fire sprinkler subcontractor needs a call today. Approved as noted means the item can go ahead if the notes are followed. Review stamps vary by firm, so read the actual wording on each returned drawing.<\/p>\n<h2 id=\"lead-time\">How far ahead should shop drawings be submitted?<\/h2>\n<p>Submit each shop drawing early enough to cover preparation, the design team\u2019s review, one round of corrections and the fabrication and delivery time before the item is needed on site. The safest way to find that date is to plan backward from the install date.<\/p>\n<p>Here is the back-plan for the aluminum storefront, which must be installed on Monday, March 15, 2027. Lead times are a sample for this job; ask each supplier for theirs. The bold row is the submission deadline.<\/p>\n<div class=\"wg-table-wrap\">\n<div class=\"wg-table-wrap\"><table>\n<thead>\n<tr>\n<th style=\"white-space:nowrap\">Step<\/th>\n<th style=\"text-align:right;white-space:nowrap\">Weeks<\/th>\n<th style=\"white-space:nowrap\">Must\u00a0be\u00a0done\u00a0by<\/th>\n<\/tr>\n<\/thead>\n<tbody>\n<tr>\n<td style=\"white-space:nowrap\"><strong>Storefront\u00a0installed<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap\"><\/td>\n<td>Mar 15, 2027<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap\"><strong>Fabrication\u00a0and\u00a0delivery<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap\">6<\/td>\n<td>Start by Feb 1<\/td>\n<\/tr>\n<tr>\n<td><strong>Allowance for one resubmittal<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap\">2<\/td>\n<td>Approved by Jan 18<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap\"><strong>Architect\u00a0review<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap\">2<\/td>\n<td><strong>Submit by Jan 4<\/strong><\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap\"><strong>Supplier\u00a0prepares\u00a0drawings<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap\">3<\/td>\n<td>Start by Dec 14, 2026<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap\"><strong>Total<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap\"><strong>13<\/strong><\/td>\n<td><\/td>\n<\/tr>\n<\/tbody>\n<\/table><\/div>\n<\/div>\n<p><strong>What this tells you:<\/strong> the storefront drawings must start 13 weeks before installation, in mid-December, even though the storefront goes in during March. The storefront in the log above was submitted on January 4 and approved on time, so fabrication can start. Put these submission dates into the job schedule as tasks so they move with everything else; our guide on <a href=\"\/blog\/how-to-create-a-construction-schedule\/\">how to create a construction schedule<\/a> shows how.<\/p>\n<h2 id=\"process\">How to manage shop drawings, step by step<\/h2>\n<ol>\n<li><strong>List every required shop drawing<\/strong> from the specifications at the start of the job. Each specification section says which submittals it needs.<\/li>\n<li><strong>Back-plan each one<\/strong> from its install date, using the supplier\u2019s lead time and the review period in the contract.<\/li>\n<li><strong>Make submission a condition of each subcontract or purchase order,<\/strong> with the due date written in. Our guide to <a href=\"\/blog\/construction-purchase-order\/\">construction purchase orders<\/a> covers what to put on the order.<\/li>\n<li><strong>Review before you submit.<\/strong> Check dimensions, quantities and coordination with other trades against the drawings and specifications. Return incomplete drawings to the subcontractor rather than passing them on.<\/li>\n<li><strong>Log every submission and return<\/strong> with dates and the review action.<\/li>\n<li><strong>Distribute approved drawings<\/strong> to the field and the fabricator the same day, and mark old versions as superseded.<\/li>\n<li><strong>Check installed work against the approved drawing<\/strong> during inspections; see <a href=\"\/blog\/how-to-inspect-construction-work\/\">how to inspect construction work<\/a>.<\/li>\n<\/ol>\n<h2 id=\"mistakes\">Common shop drawing mistakes<\/h2>\n<ul>\n<li><strong>Passing drawings straight through.<\/strong> The contractor\u2019s review exists to catch coordination problems before the architect sees them.<\/li>\n<li><strong>Treating approval as a change.<\/strong> An approved drawing that differs from the contract does not change the contract without a change order.<\/li>\n<li><strong>No allowance for resubmittal.<\/strong> Plan for at least one round of corrections on complex items such as stairs and steel.<\/li>\n<li><strong>Building from a superseded version.<\/strong> Keep only the latest approved drawing in the field.<\/li>\n<li><strong>Late submittals from one trade.<\/strong> A missing sprinkler layout can hold up ceilings, ductwork and inspections.<\/li>\n<li><strong>Using shop drawings to ask design questions.<\/strong> Ask through an RFI so the answer is on record.<\/li>\n<\/ul>\n<h2 id=\"spreadsheet-to-wisegrid\">Moving the shop drawing log from a spreadsheet to Wisegrid<\/h2>\n<p>Most contractors keep the shop drawing log in Excel or inside a larger submittal log, which works while one project engineer owns it. It gets harder when subcontractors, the superintendent and the architect all need the current status. Wisegrid, a spreadsheet-native work management app, keeps the same grid but shares it live: status is a dropdown, the Due back column can be a formula from the submission date, and a date-triggered automation can flag any row still In review after its due date.<\/p>\n<p>Wisegrid does not have a dedicated shop drawing template, so start from the columns in the log above or from the general <a href=\"\/blog\/construction-project-management-templates\/\">construction project management templates<\/a>, and roll the open items into the <a href=\"\/templates\/construction-project-dashboard\/\">construction project dashboard<\/a>. Viewers are free, so subcontractors and the design team can see the log without a paid seat. Record deliveries of approved items in your <a href=\"\/blog\/construction-daily-report\/\">construction daily report<\/a>.<\/p>\n<h2 id=\"faq\">FAQ<\/h2>\n<h3 id=\"what-is-the-difference-between-shop-drawings-and-submittals\">What is the difference between shop drawings and submittals?<\/h3>\n<p>Shop drawings are one type of submittal. Submittals is the wider term for everything the contractor sends the design team for review, which under AIA A201 includes shop drawings, product data and samples. Shop drawings are prepared specially for the project, while product data is the manufacturer\u2019s standard information, such as cut sheets and performance charts.<\/p>\n<h3 id=\"who-prepares-shop-drawings\">Who prepares shop drawings?<\/h3>\n<p>The subcontractor, fabricator, manufacturer or supplier who will make the item usually prepares the shop drawings. The general contractor reviews them, coordinates them with other trades and submits them to the architect or engineer. AIA A201 section 3.12.1 covers drawings prepared by the contractor or a subcontractor, sub-subcontractor, manufacturer, supplier or distributor.<\/p>\n<h3 id=\"are-shop-drawings-contract-documents\">Are shop drawings contract documents?<\/h3>\n<p>No. AIA A201 section 3.12.4 says shop drawings, product data, samples and similar submittals are not contract documents, and the Engineers Joint Contract Documents Committee (EJCDC) documents say the same. Their role is to show how the contractor will meet the contract, so an approved shop drawing does not change the contract unless a change order is issued.<\/p>\n<h3 id=\"what-is-the-difference-between-shop-drawings-and-as-built-drawings\">What is the difference between shop drawings and as-built drawings?<\/h3>\n<p>Shop drawings are prepared before fabrication to show how an item will be made and installed. As-built drawings, also called record drawings, are marked up during and after construction to show what was actually built, including changes made in the field. Shop drawings look forward; as-built drawings record the result for the owner.<\/p>\n<h3 id=\"how-long-does-shop-drawing-review-take\">How long does shop drawing review take?<\/h3>\n<p>The contract or specifications set the review period, and it varies by project and by the size of the submittal. Whatever the period, plan for at least one resubmittal on complex items and put the submission dates into the schedule. AIA\u2019s guidance is to establish a submittal schedule early in the project if the contract does not already address it.<\/p>\n<h2 id=\"sources\">Sources<\/h2>\n<ul>\n<li><a href=\"https:\/\/ejcdc.org\/shop-drawings-and-submittalspart-1-definition-purpose-and-necessityby-kevin-obeirne-pe\/\" target=\"_blank\" rel=\"noopener\">EJCDC: Shop drawings and submittals, part 1 (Kevin O\u2019Beirne, PE)<\/a><\/li>\n<li><a href=\"https:\/\/learn.aiacontracts.com\/articles\/what-is-a-submittal-in-construction\/\" target=\"_blank\" rel=\"noopener\">AIA Contract Documents: What is a submittal in construction?<\/a><\/li>\n<\/ul>\n<hr>\n<h3 id=\"keep-every-shop-drawing-on-one-live-log\">Keep every shop drawing on one live log<\/h3>\n<p>Track shop drawings next to your <a href=\"\/blog\/construction-submittal-log\/\">submittal log<\/a> and <a href=\"\/blog\/construction-punch-list\/\">punch list<\/a>, and see what is late on the <a href=\"\/templates\/construction-project-dashboard\/\">construction project dashboard<\/a>.<\/p>\n<p><strong><a href=\"\/signup\/\">Start free \u2192<\/a><\/strong> \u00b7 <a href=\"\/for\/construction\/\">Wisegrid for construction<\/a> \u00b7 <a href=\"\/blog\/construction-project-management-templates\/\">Construction templates<\/a><\/p>\n<hr>\n<blockquote>\n<p><strong>About the author<\/strong> <strong><a href=\"\/blog\/author\/ryan-kramer\/\">Ryan Kramer<\/a><\/strong> is the founder of Wisegrid, a higher-capacity work management grid built around a 1,000,000-cell-per-sheet limit, date-triggered automations with run history, and cross-sheet reporting. He writes about the project management documents teams actually keep updated. <a href=\"\/blog\/author\/ryan-kramer\/\">More from Ryan \u2192<\/a><\/p>\n<\/blockquote>\n","protected":false},"excerpt":{"rendered":"<p>Shop drawings explained: what they are, how they differ from submittals and design drawings, a six-item shop drawing log and how to back-plan review dates.<\/p>\n","protected":false},"author":2,"featured_media":0,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[3],"tags":[54,7],"class_list":["post-230","post","type-post","status-publish","format-standard","hentry","category-construction","tag-shop-drawings","tag-submittals"],"_links":{"self":[{"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/posts\/230","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/users\/2"}],"replies":[{"embeddable":true,"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/comments?post=230"}],"version-history":[{"count":1,"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/posts\/230\/revisions"}],"predecessor-version":[{"id":231,"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/posts\/230\/revisions\/231"}],"wp:attachment":[{"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/media?parent=230"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/categories?post=230"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/tags?post=230"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}