{"id":178,"date":"2026-11-12T10:06:44","date_gmt":"2026-11-12T10:06:44","guid":{"rendered":"https:\/\/wisegrid.co\/blog\/?p=178"},"modified":"2026-11-01T10:07:19","modified_gmt":"2026-11-01T10:07:19","slug":"construction-cash-flow-forecast","status":"publish","type":"post","link":"https:\/\/wisegrid.co\/blog\/construction-cash-flow-forecast\/","title":{"rendered":"Construction Cash Flow Forecast: A Simple Weekly Method (2026)"},"content":{"rendered":"<p><em>By <a href=\"\/blog\/author\/ryan-kramer\/\">Ryan Kramer<\/a>, founder of Wisegrid. Last updated November 2026.<\/em><\/p>\n<p>A construction cash flow forecast estimates the money coming in and going out of your business, week by week, for the next six to thirteen weeks. Cash in comes from deposits, draws and payment applications. Cash out is payroll, materials, subcontractors and overhead. The forecast shows the week your bank balance will be lowest, while there is still time to do something about it.<\/p>\n<p>Construction is hard on cash. You pay crews every week, but owners pay monthly, lenders inspect before they release draws, and retainage sits unpaid until the end. A job can be profitable and still leave you short on a Friday. This guide shows a simple weekly method, a six-week example with three jobs, where cash gets stuck, and the fixes that work.<\/p>\n<blockquote>\n<p style=\"margin:0\"><strong>Key takeaways<\/strong><\/p>\n<p style=\"margin:0.55em 0 0\">\u2013 <strong>Forecast weekly, not monthly.<\/strong> Payroll is weekly, so a monthly view hides the week you run short.<\/p>\n<p style=\"margin:0.55em 0 0\">\u2013 <strong>Use the dates money actually arrives<\/strong>, not the dates you send invoices.<\/p>\n<p style=\"margin:0.55em 0 0\">\u2013 <strong>Profit is not cash.<\/strong> Retainage, unpaid invoices and unbilled work all sit between the two.<\/p>\n<p style=\"margin:0.55em 0 0\">\u2013 <strong>Set a minimum balance<\/strong> and act on any week that falls below it.<\/p>\n<p style=\"margin:0.55em 0 0\">\u2013 <strong>Your draw schedule and payment applications drive cash in.<\/strong> Bill on time, every time.<\/p>\n<\/blockquote>\n<nav class=\"wg-toc\" aria-label=\"Table of contents\">\n<div class=\"wg-toc-eyebrow\"><span class=\"lp-dot\" aria-hidden=\"true\"><\/span> On this page<\/div>\n<ul>\n<li><a href=\"#what-is-a-cash-flow-forecast\">What is a construction cash flow forecast?<\/a><\/li>\n<li><a href=\"#cash-in\">Where does cash in come from?<\/a><\/li>\n<li><a href=\"#cash-flow-example\">Cash flow forecast example<\/a><\/li>\n<li><a href=\"#where-cash-gets-stuck\">Where does cash get stuck?<\/a><\/li>\n<li><a href=\"#how-to-build\">How to build a weekly cash flow forecast<\/a><\/li>\n<li><a href=\"#how-to-fix-a-low-week\">How to fix a low cash week<\/a><\/li>\n<li><a href=\"#common-mistakes\">Common cash flow forecasting mistakes<\/a><\/li>\n<li><a href=\"#from-spreadsheet-to-shared-forecast\">From spreadsheet to a shared cash forecast<\/a><\/li>\n<li><a href=\"#faq\">FAQ<\/a><\/li>\n<\/ul>\n<\/nav>\n<h2 id=\"what-is-a-cash-flow-forecast\">What is a construction cash flow forecast?<\/h2>\n<p>It is a list of weeks with four numbers each: cash in, cash out, net and ending balance. Ending balance is last week\u2019s balance plus this week\u2019s net. The FDIC and U.S. Small Business Administration describe a cash flow projection as a forward-looking estimate of cash in and out that you revise as things change. That last part matters. A forecast is updated every week, not built once.<\/p>\n<p>It is not the same as your profit and loss statement. Your accountant may record revenue when work is done. The forecast only counts money when it lands in the bank.<\/p>\n<h2 id=\"cash-in\">Where does cash in come from?<\/h2>\n<ul>\n<li><strong>Deposits<\/strong> on new contracts, within any limits your state sets.<\/li>\n<li><strong>Draws<\/strong> paid when milestones are reached. Our <a href=\"\/blog\/construction-draw-schedule\/\">construction draw schedule guide<\/a> shows how to set them.<\/li>\n<li><strong>Monthly payment applications<\/strong> on commercial work, billed against a <a href=\"\/blog\/schedule-of-values\/\">schedule of values<\/a> and usually paid 15 to 45 days later, depending on the contract. Our guide to the American Institute of Architects (AIA) <a href=\"\/blog\/aia-g702\/\">G702 payment application<\/a> shows how each one is calculated.<\/li>\n<li><strong>Approved change orders<\/strong>, once billed. Pending ones do not count yet.<\/li>\n<li><strong>Retainage releases<\/strong>, often months after the work is done.<\/li>\n<\/ul>\n<p>For each one, use the date you expect the money in the bank, based on how that owner or lender has actually paid before.<\/p>\n<h3 id=\"watch-construction-draw-schedule-get-paid-at-every-phase-2-minutes\">Watch: Construction Draw Schedule: Get Paid at Every Phase (2 minutes)<\/h3>\n<div class=\"wg-video\" style=\"position:relative;width:100%;max-width:720px;aspect-ratio:16\/9;margin:0 0 1.4em;border-radius:12px;overflow:hidden;background:#0f172a\"><iframe src=\"https:\/\/www.youtube.com\/embed\/RPcZ89fSdp0?rel=0&amp;playsinline=1\" title=\"Construction Draw Schedule: Get Paid at Every Phase\" style=\"position:absolute;top:0;left:0;width:100%;height:100%;border:0\" allow=\"accelerometer; clipboard-write; encrypted-media; gyroscope; picture-in-picture; web-share\" referrerpolicy=\"strict-origin-when-cross-origin\" allowfullscreen loading=\"lazy\"><\/iframe><\/div>\n<p style=\"margin:-0.6em 0 1.4em;font-size:15px\"><a href=\"https:\/\/www.youtube.com\/watch?v=RPcZ89fSdp0\" target=\"_blank\" rel=\"noopener\">Watch \u201cConstruction Draw Schedule: Get Paid at Every Phase\u201d on YouTube \u2192<\/a><\/p>\n<h2 id=\"cash-flow-example\">Cash flow forecast example<\/h2>\n<p>A small contractor with three jobs, starting with $62,000 in the bank. Cash in includes a new deposit, a payment application, and two draws. Cash out includes weekly payroll, materials and subcontractor payments. The minimum balance the owner wants to keep is $25,000. The bold row is the low point.<\/p>\n<div class=\"wg-table-wrap\">\n<div class=\"wg-table-wrap\"><table>\n<thead>\n<tr>\n<th style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Week<\/th>\n<th style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">Cash\u00a0in<\/th>\n<th style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">Cash\u00a0out<\/th>\n<th style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">Net<\/th>\n<th style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">Ending\u00a0cash<\/th>\n<\/tr>\n<\/thead>\n<tbody>\n<tr>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>Week\u00a01<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$18,600<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$41,000<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">\u2212$22,400<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$39,600<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>Week\u00a02<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$50,895<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$38,500<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$12,395<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$51,995<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>Week\u00a03<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$0<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$44,200<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">\u2212$44,200<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>$7,795<\/strong><\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>Week\u00a04<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$46,500<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$36,800<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$9,700<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$17,495<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>Week\u00a05<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$37,200<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$39,000<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">\u2212$1,800<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$15,695<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>Week\u00a06<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$62,300<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$40,100<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$22,200<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$37,895<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>Total<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>$215,495<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>$239,600<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>\u2212$24,105<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>$37,895<\/strong><\/td>\n<\/tr>\n<\/tbody>\n<\/table><\/div>\n<\/div>\n<p><strong>What this tells you:<\/strong> the business ends six weeks with less cash than it started, and it spends <strong>weeks 3 to 5 below the $25,000 minimum<\/strong>. Week 3 is the danger: a $44,200 week with nothing coming in. The $46,500 draw in week 4 is the one that fixes it, so that invoice needs to go out today, not when the office catches up.<\/p>\n<h2 id=\"where-cash-gets-stuck\">Where does cash get stuck?<\/h2>\n<p>Cash that you have earned but not received is the first place to look. For the same contractor:<\/p>\n<div class=\"wg-table-wrap\">\n<div class=\"wg-table-wrap\"><table>\n<thead>\n<tr>\n<th style=\"white-space:nowrap\">Earned\u00a0but\u00a0not\u00a0in\u00a0the\u00a0bank<\/th>\n<th style=\"text-align:right;white-space:nowrap\">Amount<\/th>\n<\/tr>\n<\/thead>\n<tbody>\n<tr>\n<td style=\"white-space:nowrap\"><strong>Retainage\u00a0held<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap\">$28,600<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap\"><strong>Invoiced,\u00a0not\u00a0paid<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap\">$46,500<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap\"><strong>Pending\u00a0change\u00a0orders<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap\">$7,590<\/td>\n<\/tr>\n<tr>\n<td><strong>Work done, not yet billed<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap\">$12,000<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap\"><strong>Total\u00a0tied\u00a0up<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap\"><strong>$94,690<\/strong><\/td>\n<\/tr>\n<\/tbody>\n<\/table><\/div>\n<\/div>\n<p><strong>What this tells you:<\/strong> $94,690 is sitting with owners and lenders, more than enough to cover the week 3 gap. Each line has a different fix. Retainage needs closeout paperwork, as the <a href=\"\/blog\/retainage-in-construction\/\">retainage guide<\/a> explains. Pending changes need signatures, covered in our <a href=\"\/blog\/stop-eating-change-orders\/\">change order process guide<\/a>. Unbilled work needs an invoice.<\/p>\n<h2 id=\"how-to-build\">How to build a weekly cash flow forecast<\/h2>\n<ol>\n<li><strong>Start with today\u2019s bank balance.<\/strong> The real one, not the accounting balance.<\/li>\n<li><strong>List cash in by week<\/strong> for every job: deposits, draws, payment applications and retainage. Use realistic payment dates.<\/li>\n<li><strong>List cash out by week<\/strong>: payroll, subcontractor payments, material bills, equipment, rent, insurance and loan payments. Signed purchase orders and subcontracts tell you what is coming; keep them in a <a href=\"\/templates\/purchase-order-template\/\">purchase order template<\/a>. Your <a href=\"\/blog\/construction-job-costing\/\">job costing<\/a> sheet already tracks these as committed costs.<\/li>\n<li><strong>Calculate net and ending cash<\/strong> for each week.<\/li>\n<li><strong>Set a minimum balance<\/strong>, such as two weeks of payroll, and flag any week below it.<\/li>\n<li><strong>Update it every week<\/strong> with what actually happened, and roll one more week onto the end.<\/li>\n<\/ol>\n<h2 id=\"how-to-fix-a-low-week\">How to fix a low cash week<\/h2>\n<ul>\n<li><strong>Bill faster.<\/strong> Send draws the day the milestone is reached and payment applications on the contract\u2019s billing date.<\/li>\n<li><strong>Chase what is late.<\/strong> Call about every invoice past its due date, starting with the largest.<\/li>\n<li><strong>Get pending change orders signed<\/strong> so they can go on the next bill.<\/li>\n<li><strong>Line up supplier terms.<\/strong> Ask for 30-day terms on large material orders before you need them.<\/li>\n<li><strong>Match subcontractor payments to your receipts.<\/strong> If your subcontracts say you pay when you are paid, follow the timing your contract and state law allow.<\/li>\n<li><strong>Use a line of credit for timing gaps, not for losses.<\/strong> If the forecast keeps falling, the problem is margin, not timing.<\/li>\n<\/ul>\n<h2 id=\"common-mistakes\">Common cash flow forecasting mistakes<\/h2>\n<ul>\n<li><strong>Using invoice dates instead of payment dates.<\/strong> The forecast looks great and the bank account does not.<\/li>\n<li><strong>Forgetting retainage.<\/strong> Five to ten percent of every bill does not arrive until the end.<\/li>\n<li><strong>Leaving out overhead.<\/strong> Rent, insurance, trucks and the office manager still need paying.<\/li>\n<li><strong>Counting pending change orders as cash.<\/strong> They are not money until they are signed, billed and paid.<\/li>\n<li><strong>Building it once.<\/strong> A forecast that is not updated weekly is just a guess with a date on it.<\/li>\n<\/ul>\n<h2 id=\"from-spreadsheet-to-shared-forecast\">From spreadsheet to a shared cash forecast<\/h2>\n<p>Most contractors who forecast cash do it in a spreadsheet, and that works. The hard part is the inputs. Draw dates live in one file, payment applications in another, committed costs in a third, and the forecast is only as good as the last time someone copied them across.<\/p>\n<p>In Wisegrid, the forecast can read draw dates from each job\u2019s <a href=\"\/templates\/construction-draw-schedule-template\/\">draw schedule template<\/a> and committed costs from the <a href=\"\/templates\/construction-job-costing-template\/\">construction job costing template<\/a>, so updating it on Friday takes minutes. The weekly totals sit next to the <a href=\"\/templates\/construction-project-dashboard\/\">construction project dashboard<\/a> (our <a href=\"\/blog\/construction-project-dashboard\/\">construction dashboard guide<\/a> explains what else belongs there), and your bookkeeper or partner can view it for free.<\/p>\n<h2 id=\"faq\">FAQ<\/h2>\n<h3 id=\"how-far-ahead-should-a-contractor-forecast-cash\">How far ahead should a contractor forecast cash?<\/h3>\n<p>Six to thirteen weeks is common for a weekly forecast. Six weeks covers most payment cycles on small jobs. Thirteen weeks, about one quarter, helps when you are bidding larger work or planning to hire. Keep it weekly either way.<\/p>\n<h3 id=\"why-do-profitable-contractors-run-out-of-cash\">Why do profitable contractors run out of cash?<\/h3>\n<p>Because they pay costs before they get paid. Payroll and suppliers come first, while owners pay monthly, lenders inspect before releasing draws, and retainage is held until the end. Fast growth makes it worse, since each new job needs cash up front.<\/p>\n<h3 id=\"what-is-a-good-minimum-cash-balance-for-a-contractor\">What is a good minimum cash balance for a contractor?<\/h3>\n<p>Many owners aim for at least two to four weeks of payroll and fixed costs. The right number depends on how reliably your customers pay and whether you have a line of credit. Pick a number, put it on the forecast and act when a week falls below it.<\/p>\n<h3 id=\"is-a-cash-flow-forecast-the-same-as-a-budget\">Is a cash flow forecast the same as a budget?<\/h3>\n<p>No. A budget plans what a job or year should cost and earn. A cash flow forecast plans when money moves in and out of the bank. You need both, and the forecast uses numbers from the budget.<\/p>\n<h2 id=\"sources\">Sources<\/h2>\n<ul>\n<li><a href=\"https:\/\/www.fdic.gov\/consumer-resource-center\/mssb-m10-pg.pdf\" target=\"_blank\" rel=\"noopener\">FDIC and SBA Money Smart for Small Business, Module 10: Managing Cash Flow<\/a><\/li>\n<\/ul>\n<hr>\n<h3 id=\"see-the-low-week-before-it-arrives\">See the low week before it arrives<\/h3>\n<p>Keep draws, costs and cash in one shared Wisegrid workspace. Start with the <a href=\"\/templates\/construction-draw-schedule-template\/\">draw schedule template<\/a>, the <a href=\"\/templates\/construction-job-costing-template\/\">construction job costing template<\/a> and the <a href=\"\/templates\/project-budget-template\/\">project budget template<\/a>.<\/p>\n<p><strong><a href=\"\/signup\/\">Start free \u2192<\/a><\/strong> \u00b7 <a href=\"\/blog\/construction-draw-schedule\/\">Draw schedule guide \u2192<\/a> \u00b7 <a href=\"\/blog\/retainage-in-construction\/\">Retainage guide \u2192<\/a><\/p>\n<hr>\n<blockquote>\n<p><strong>About the author<\/strong> <strong><a href=\"\/blog\/author\/ryan-kramer\/\">Ryan Kramer<\/a><\/strong> is the founder of Wisegrid, a higher-capacity work management grid built around a 1,000,000-cell-per-sheet limit, date-triggered automations with run history, and cross-sheet reporting. He writes about the project management documents teams actually keep updated. <a href=\"\/blog\/author\/ryan-kramer\/\">More from Ryan \u2192<\/a><\/p>\n<\/blockquote>\n","protected":false},"excerpt":{"rendered":"<p>How small contractors forecast cash flow week by week: a 6-week example with three jobs, where cash gets stuck, and how to fix a low week before it hits.<\/p>\n","protected":false},"author":2,"featured_media":0,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[3],"tags":[24,18],"class_list":["post-178","post","type-post","status-publish","format-standard","hentry","category-construction","tag-cash-flow","tag-construction-finance"],"_links":{"self":[{"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/posts\/178","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/users\/2"}],"replies":[{"embeddable":true,"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/comments?post=178"}],"version-history":[{"count":1,"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/posts\/178\/revisions"}],"predecessor-version":[{"id":179,"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/posts\/178\/revisions\/179"}],"wp:attachment":[{"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/media?parent=178"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/categories?post=178"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/tags?post=178"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}