{"id":154,"date":"2026-11-05T10:38:00","date_gmt":"2026-11-05T10:38:00","guid":{"rendered":"https:\/\/wisegrid.co\/blog\/?p=154"},"modified":"2026-11-01T03:39:23","modified_gmt":"2026-11-01T03:39:23","slug":"retainage-in-construction","status":"publish","type":"post","link":"https:\/\/wisegrid.co\/blog\/retainage-in-construction\/","title":{"rendered":"Retainage in Construction: How It Works, With Examples (2026)"},"content":{"rendered":"<p><em>By <a href=\"\/blog\/author\/ryan-kramer\/\">Ryan Kramer<\/a>, founder of Wisegrid. Last updated November 2026.<\/em><\/p>\n<p>Retainage in construction is a share of each progress payment that the owner holds back until the job is finished. It is usually 5% to 10% of the work billed. The money still belongs to the contractor who earned it. It is simply paid later, once the work is complete and the closeout items are done.<\/p>\n<p>Retainage protects the owner if a contractor walks away or leaves defects behind. For contractors and subcontractors it is often their whole profit on a job, sitting in someone else\u2019s bank account for months. This guide explains how retainage is calculated, what rates are allowed, a worked example, and how to track it so it actually gets paid.<\/p>\n<blockquote>\n<p style=\"margin:0\"><strong>Key takeaways<\/strong><\/p>\n<p style=\"margin:0.55em 0 0\">\u2013 <strong>Retainage is earned money paid late.<\/strong> It is held from each payment request and released at the end of the job.<\/p>\n<p style=\"margin:0.55em 0 0\">\u2013 <strong>Rates of 5% to 10% are common<\/strong>, but your contract sets the rate and many states cap it, especially on public work.<\/p>\n<p style=\"margin:0.55em 0 0\">\u2013 <strong>Many contracts cut retainage at 50% complete<\/strong>, so total retainage ends up near 5% of the contract.<\/p>\n<p style=\"margin:0.55em 0 0\">\u2013 <strong>Retainage can be larger than a subcontractor\u2019s profit.<\/strong> That turns a profitable job into a cash shortfall until release.<\/p>\n<p style=\"margin:0.55em 0 0\">\u2013 <strong>Release does not happen by itself.<\/strong> You bill for it, with closeout documents, and follow up until it is paid.<\/p>\n<\/blockquote>\n<nav class=\"wg-toc\" aria-label=\"Table of contents\">\n<div class=\"wg-toc-eyebrow\"><span class=\"lp-dot\" aria-hidden=\"true\"><\/span> On this page<\/div>\n<ul>\n<li><a href=\"#what-is-retainage\">What is retainage in construction?<\/a><\/li>\n<li><a href=\"#why-owners-hold-retainage\">Why do owners hold retainage?<\/a><\/li>\n<li><a href=\"#typical-retainage-rates\">How much retainage is typical?<\/a><\/li>\n<li><a href=\"#retainage-example\">How is retainage calculated? An example<\/a><\/li>\n<li><a href=\"#retainage-and-subcontractors\">Why retainage hurts subcontractors most<\/a><\/li>\n<li><a href=\"#when-is-retainage-released\">When is retainage released?<\/a><\/li>\n<li><a href=\"#how-to-track-retainage\">How to track retainage, step by step<\/a><\/li>\n<li><a href=\"#common-mistakes\">Common retainage mistakes<\/a><\/li>\n<li><a href=\"#from-spreadsheet-to-shared-tracker\">From spreadsheet to a shared retainage tracker<\/a><\/li>\n<li><a href=\"#faq\">FAQ<\/a><\/li>\n<\/ul>\n<\/nav>\n<h2 id=\"what-is-retainage\">What is retainage in construction?<\/h2>\n<p>Retainage (also called retention) is money withheld from each progress payment as security. The owner holds it back from the general contractor. The general contractor usually holds the same percentage back from each subcontractor. It is paid out when the work is substantially complete, or when the whole contract is finished, depending on the contract.<\/p>\n<p>Retainage shows up on every payment request. If you bill against a <a href=\"\/blog\/schedule-of-values\/\">schedule of values<\/a>, retainage is calculated on the total completed and stored to date, then subtracted before the payment due is worked out. On a home built with a construction loan, the lender may hold retainage from each draw instead. Our <a href=\"\/blog\/construction-draw-schedule\/\">construction draw schedule guide<\/a> covers how draws work.<\/p>\n<h2 id=\"why-owners-hold-retainage\">Why do owners hold retainage?<\/h2>\n<p>Owners hold retainage to keep leverage until the job is done. It gives them money to finish or fix work if a contractor does not. It also gives the contractor a reason to complete the last items on the job, such as the <a href=\"\/blog\/construction-punch-list\/\">construction punch list<\/a>, warranties and manuals.<\/p>\n<p>The cost of that protection lands on the contractor. A general contractor or subcontractor has already paid its crews and suppliers for the work. Retainage means it waits months, sometimes more than a year, for money it has already spent.<\/p>\n<h2 id=\"typical-retainage-rates\">How much retainage is typical?<\/h2>\n<p>Most private contracts set retainage between 5% and 10%. The rate is written in the owner\u2013contractor agreement, and subcontracts usually copy it. The law can override the contract, and the rules have been tightening:<\/p>\n<ul>\n<li><strong>Federal construction contracts.<\/strong> Under Federal Acquisition Regulation (FAR) 32.103, retainage is meant for when a contractor is not making satisfactory progress. It may not exceed 10% of the approved amount, and it should be paid promptly once the contract is complete.<\/li>\n<li><strong>California private projects.<\/strong> For contracts signed on or after January 1, 2026, Civil Code section 8811 caps retention at 5% of each payment and of the total contract. Small residential projects of four stories or fewer are exempt.<\/li>\n<li><strong>New York private projects.<\/strong> Since December 19, 2025, a 5% cap on private contracts over $150,000 can no longer be waived by contract.<\/li>\n<li><strong>Public projects in most states<\/strong> have their own caps and release deadlines, and many are lower than 10%.<\/li>\n<\/ul>\n<p><strong>Rules change often and differ by state and by project type.<\/strong> Check the current law for your state, and ask a construction lawyer if your contract\u2019s rate looks higher than allowed. This article is general information, not legal advice.<\/p>\n<h2 id=\"retainage-example\">How is retainage calculated? An example<\/h2>\n<p>A $600,000 tenant build-out with 10% retainage until the job is 50% complete. After that, the contract says no more retainage is held on new work. The table shows five monthly payment requests. The bold row is the point where retainage stops growing.<\/p>\n<div class=\"wg-table-wrap\">\n<div class=\"wg-table-wrap\"><table>\n<thead>\n<tr>\n<th style=\"white-space:nowrap;padding:11px 14px;font-size:14px\">Payment\u00a0request<\/th>\n<th style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">Work\u00a0this\u00a0period<\/th>\n<th style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">Retainage\u00a0held<\/th>\n<th style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">Paid<\/th>\n<th style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">Held\u00a0to\u00a0date<\/th>\n<\/tr>\n<\/thead>\n<tbody>\n<tr>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>Request\u00a01<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$90,000<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$9,000<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$81,000<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$9,000<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>Request\u00a02<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$120,000<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$12,000<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$108,000<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$21,000<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>Request\u00a03\u00a0(50%)<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$90,000<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$9,000<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$81,000<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>$30,000<\/strong><\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>Request\u00a04<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$150,000<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$0<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$150,000<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$30,000<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>Request\u00a05<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$150,000<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$0<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$150,000<\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\">$30,000<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>Total<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>$600,000<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>$30,000<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>$570,000<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap;padding:11px 14px;font-size:14px\"><strong>$30,000<\/strong><\/td>\n<\/tr>\n<\/tbody>\n<\/table><\/div>\n<\/div>\n<p><strong>What this tells you:<\/strong> the contractor has billed the full $600,000 but has been paid $570,000. The last <strong>$30,000 is retainage<\/strong>, which is 5% of the contract. It is paid only after the final payment request for retainage is approved.<\/p>\n<p>The formula on each request is simple: <strong>retainage = work billed this period \u00d7 retainage rate<\/strong>. Many payment forms calculate it on the total to date instead, then subtract retainage already held. Both give the same answer if the rate has not changed. The <a href=\"\/blog\/schedule-of-values\/\">schedule of values example<\/a> shows the same math on a full payment request summary.<\/p>\n<h2 id=\"retainage-and-subcontractors\">Why retainage hurts subcontractors most<\/h2>\n<p>Retainage often equals or beats the profit on a subcontract. Here is a drywall subcontractor on an $80,000 subcontract with an 8% profit margin and 10% retainage. The bold row is the cash the subcontractor is short when its work is finished.<\/p>\n<div class=\"wg-table-wrap\">\n<div class=\"wg-table-wrap\"><table>\n<thead>\n<tr>\n<th style=\"white-space:nowrap\">Drywall\u00a0subcontract<\/th>\n<th style=\"text-align:right;white-space:nowrap\">Amount<\/th>\n<\/tr>\n<\/thead>\n<tbody>\n<tr>\n<td style=\"white-space:nowrap\"><strong>Subcontract\u00a0value<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap\">$80,000<\/td>\n<\/tr>\n<tr>\n<td><strong>Cost of the work (92%)<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap\">$73,600<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap\"><strong>Expected\u00a0profit\u00a0(8%)<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap\">$6,400<\/td>\n<\/tr>\n<tr>\n<td style=\"white-space:nowrap\"><strong>Retainage\u00a0held\u00a0(10%)<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap\">$8,000<\/td>\n<\/tr>\n<tr>\n<td><strong>Paid so far (90%)<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap\">$72,000<\/td>\n<\/tr>\n<tr>\n<td><strong>Cash short at finish<\/strong><\/td>\n<td style=\"text-align:right;white-space:nowrap\"><strong>\u2212$1,600<\/strong><\/td>\n<\/tr>\n<\/tbody>\n<\/table><\/div>\n<\/div>\n<p><strong>What this tells you:<\/strong> the subcontractor has spent $73,600 and been paid $72,000. Its whole profit, and $1,600 more, sits in retainage. If drywall finishes in month four of a 14-month job, that money may wait 10 months. Early trades such as site work, concrete and framing feel this the most.<\/p>\n<p>This is why your <a href=\"\/blog\/construction-job-costing\/\">construction job costing<\/a> should show retainage owed to you next to each job\u2019s profit. A job can look profitable on paper and still drain cash.<\/p>\n<h2 id=\"when-is-retainage-released\">When is retainage released?<\/h2>\n<p>Retainage is released when the contract says, usually at substantial completion or final completion. Substantial completion means the building can be used for its purpose, even if small items remain. Common release steps:<\/p>\n<ul>\n<li><strong>Reduction partway through.<\/strong> Many contracts drop the rate at 50% complete, as in the example above.<\/li>\n<li><strong>Release at substantial completion<\/strong>, minus an amount held back for unfinished punch list items.<\/li>\n<li><strong>Final release after closeout.<\/strong> Punch list done, warranties, manuals, as-built drawings and final lien waivers delivered.<\/li>\n<li><strong>Early release for early trades.<\/strong> Some contracts let the general contractor release a subcontractor\u2019s retainage once its work is accepted, instead of waiting for the whole building.<\/li>\n<\/ul>\n<p>Many states also set deadlines for paying retainage once it is due, with interest if it is late. Again, check your state\u2019s rules.<\/p>\n<h2 id=\"how-to-track-retainage\">How to track retainage, step by step<\/h2>\n<ol>\n<li><strong>Read the retainage terms before you sign.<\/strong> Note the rate, any reduction point, when release is due, and what documents are needed. Make sure the subcontract rate is not higher than the prime contract rate.<\/li>\n<li><strong>Add retainage columns to your billing sheet.<\/strong> Retainage this period, retainage to date and retainage released, per job. Your <a href=\"\/blog\/schedule-of-values\/\">schedule of values<\/a> is the natural place.<\/li>\n<li><strong>Check the retainage math on every payment received.<\/strong> Payment received should equal billed this period minus retainage. Any gap needs a phone call that week.<\/li>\n<li><strong>Track retainage you hold from subcontractors separately.<\/strong> It is money you owe. Keep it next to commitments in your <a href=\"\/templates\/construction-job-costing-template\/\">job costing template<\/a>.<\/li>\n<li><strong>Start collecting closeout documents early.<\/strong> Warranties, manuals and lien waivers take weeks to gather. Track them with the punch list.<\/li>\n<li><strong>Bill for retainage as its own payment request<\/strong> the day release is allowed, and put a follow-up date on it.<\/li>\n<\/ol>\n<h2 id=\"common-mistakes\">Common retainage mistakes<\/h2>\n<ul>\n<li><strong>Forgetting to bill for it.<\/strong> Retainage is rarely paid without a request. Small amounts on finished jobs are often never collected.<\/li>\n<li><strong>Not counting it in cash flow.<\/strong> Revenue looks fine, but 5% to 10% of every job is stuck until the end.<\/li>\n<li><strong>Holding more from subcontractors than the owner holds from you.<\/strong> It strains relationships and may break state law or the prime contract.<\/li>\n<li><strong>Holding retainage on change orders by mistake, or forgetting to.<\/strong> Check whether your contract applies retainage to approved change orders. Our guide on <a href=\"\/blog\/stop-eating-change-orders\/\">handling change orders without losing money<\/a> covers the billing side.<\/li>\n<li><strong>Missing closeout paperwork.<\/strong> One missing warranty letter can hold up the whole final payment.<\/li>\n<\/ul>\n<h2 id=\"from-spreadsheet-to-shared-tracker\">From spreadsheet to a shared retainage tracker<\/h2>\n<p>A spreadsheet works for retainage on one or two jobs. It gets risky when each job has its own file, retainage is tracked in a column someone added in month three, and nobody owns the list of finished jobs with money still held.<\/p>\n<p>In Wisegrid, each job\u2019s billing sits on one sheet with retainage columns, and a <a href=\"\/templates\/construction-project-dashboard\/\">construction project dashboard<\/a> rolls up retainage owed to you and owed by you across every job. Closeout documents can live on the same sheet as the punch list, so release is not waiting on a lost email. It is still a grid, so your team can keep working the way they do in Excel. If you are comparing tools, see our <a href=\"\/for\/construction\/\">construction workspace overview<\/a> and the <a href=\"\/templates\/project-budget-template\/\">project budget template<\/a>.<\/p>\n<h2 id=\"faq\">FAQ<\/h2>\n<h3 id=\"is-retainage-the-same-as-retention\">Is retainage the same as retention?<\/h3>\n<p>Yes. Retainage and retention mean the same thing: a percentage of each progress payment held back until the work is complete. \u201cRetention\u201d is more common in California and outside the United States. \u201cRetainage\u201d is more common in the rest of the United States and on American Institute of Architects (AIA) payment forms.<\/p>\n<h3 id=\"what-is-a-typical-retainage-percentage\">What is a typical retainage percentage?<\/h3>\n<p>Between 5% and 10% of each payment. Many contracts hold 10% until the job is half complete, then stop. Several states now cap retainage at 5% on public work, and California and New York also cap it on many private projects. Your contract and your state\u2019s law decide the real number.<\/p>\n<h3 id=\"does-retainage-apply-to-change-orders\">Does retainage apply to change orders?<\/h3>\n<p>Usually yes. Approved change orders are added to the contract and billed like other work, so retainage is held on them at the same rate. Some contracts treat them differently, so check the payment terms. Track change orders as separate lines so the retainage on each one stays visible.<\/p>\n<h3 id=\"how-do-you-record-retainage-in-accounting\">How do you record retainage in accounting?<\/h3>\n<p>Contractors usually record retainage they are owed as retainage receivable, separate from regular accounts receivable. Retainage they hold from subcontractors is recorded as retainage payable. Ask your accountant how to handle it for revenue recognition and taxes, since the rules depend on your accounting method.<\/p>\n<h3 id=\"what-happens-if-retainage-is-not-paid-on-time\">What happens if retainage is not paid on time?<\/h3>\n<p>Many states require owners and general contractors to pay retainage within a set number of days after it is due, often with interest on late amounts. Start by sending a written request with your closeout documents. If it is still unpaid, your options depend on your contract and state law, so get legal advice.<\/p>\n<h2 id=\"sources\">Sources<\/h2>\n<ul>\n<li><a href=\"https:\/\/www.acquisition.gov\/far\/32.103\" target=\"_blank\" rel=\"noopener\">Federal Acquisition Regulation 32.103, Progress payments under construction contracts<\/a><\/li>\n<li><a href=\"https:\/\/www.foley.com\/insights\/publications\/2025\/11\/no-more-10-retainage-california-mandates-5-retention-cap-on-private-constructi\/\" target=\"_blank\" rel=\"noopener\">Foley &amp; Lardner: California mandates a 5% retention cap on private construction projects<\/a><\/li>\n<li><a href=\"https:\/\/www.cohenseglias.com\/?p=25444\" target=\"_blank\" rel=\"noopener\">Cohen Seglias: New York\u2019s 5% retainage limit for private projects<\/a><\/li>\n<\/ul>\n<hr>\n<h3 id=\"track-retainage-on-every-job-in-one-place\">Track retainage on every job in one place<\/h3>\n<p>Keep billing, retainage and closeout on one shared Wisegrid sheet. Start with the <a href=\"\/templates\/construction-job-costing-template\/\">construction job costing template<\/a>, roll every job into the <a href=\"\/templates\/construction-project-dashboard\/\">construction project dashboard<\/a>, and log extra work in the <a href=\"\/templates\/change-order-log-template\/\">change order log<\/a>.<\/p>\n<p><strong><a href=\"\/signup\/\">Start free \u2192<\/a><\/strong> \u00b7 <a href=\"\/blog\/schedule-of-values\/\">Schedule of values guide \u2192<\/a> \u00b7 <a href=\"\/templates\/construction-job-costing-template\/\">Job costing template \u2192<\/a><\/p>\n<hr>\n<blockquote>\n<p><strong>About the author<\/strong> <strong><a href=\"\/blog\/author\/ryan-kramer\/\">Ryan Kramer<\/a><\/strong> is the founder of Wisegrid, a higher-capacity work management grid built around a 1,000,000-cell-per-sheet limit, date-triggered automations with run history, and cross-sheet reporting. He writes about the project management documents teams actually keep updated. <a href=\"\/blog\/author\/ryan-kramer\/\">More from Ryan \u2192<\/a><\/p>\n<\/blockquote>\n","protected":false},"excerpt":{"rendered":"<p>What retainage is, how it is held on each payment request, typical rates and state caps, a worked example, and how to track it until it is released.<\/p>\n","protected":false},"author":2,"featured_media":0,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[3],"tags":[12,16],"class_list":["post-154","post","type-post","status-publish","format-standard","hentry","category-construction","tag-construction-billing","tag-retainage"],"_links":{"self":[{"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/posts\/154","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/users\/2"}],"replies":[{"embeddable":true,"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/comments?post=154"}],"version-history":[{"count":1,"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/posts\/154\/revisions"}],"predecessor-version":[{"id":155,"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/posts\/154\/revisions\/155"}],"wp:attachment":[{"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/media?parent=154"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/categories?post=154"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/wisegrid.co\/blog\/wp-json\/wp\/v2\/tags?post=154"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}